INSP-Final Inspection | 8/25/2008 | 8/25/2008 | 8/25/2008 | P | PASS |
Forrest France
|
|
|
Corrections verified for compliance, fire sprinkler permit okay for final as uprights at the plan mod. area are installed.
|
INSP-Final Inspection | 8/21/2008 | 8/22/2008 | 8/22/2008 | A | FAIL |
Forrest France
|
|
|
The four additional heads added per plan modification are not installed-need to provide drop ceiling and pendents per plan or upright sprinklers to maintain coverage throughout.
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2008 | 8/5/2008 | 8/5/2008 | P | PART |
Forrest France
|
|
|
OH fire sprinkler modifications per the original scope of work are acceptable for ceiling cover.
|
Issue and Print Permit | | | 7/24/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/23/2008 | | 7/23/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 7/23/2008 | | DONE |
Cathy Brown
|
|
|
lft vm with brodie at ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 7/23/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 7/23/2008 | | 7/23/2008 | | DONE |
Cathy Brown
|
|
|
|
Plan assigned to (Scott) | 7/21/2008 | | 7/22/2008 | | PASS |
Scott Arellano
|
|
|
*Plan Mod* 4 addtional SSP's to scope of work.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/21/2008 | | DONE |
|
|
|
Plan Mod - received 1 application / plan taken to Scott A in fire
|
Inspection Record Card- Fire | 7/17/2008 | | 7/17/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/15/2008 | | 7/17/2008 | | PASS |
|
|
|
quick permit
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2008 | | DONE |
|
|
|
|
Telephone call | | | 7/17/2008 | | DONE |
|
|
|
left vm for brodie at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/17/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/17/2008 | | DONE |
|
|
|
|
Application received | | | 7/15/2008 | | |
|
|
|
|
Pending Assignment by SAM | 7/15/2008 | | | | |
|
|
|
|