Miscellaneous action | | | 3/10/2009 | | DONE |
|
|
|
Sent for archiving
|
INSP-Final Inspection | 1/6/2009 | 1/8/2009 | 1/8/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2008 | 9/12/2008 | 9/12/2008 | P | PART |
Troy Cobbley
|
|
|
See the city approved plans for the piping for the three pendants in the bakery that are ok to cover.
|
INSP-Sprinkler Rough-in | 8/15/2008 | 8/18/2008 | 8/18/2008 | A | PART |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping rough-in passed. Work has been done in the southwest corner of the building which is not shown on the plans. Near this same location are new walls where the sprinkler protection will need to be modified and shown on a set of approved plans. Also the quick responce heads need to be changed to standard responce heads to match the other heads as per bruce and I's conversation.
|
Inspection Record Card- Fire | 8/7/2008 | | 8/7/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/7/2008 | | DONE |
|
|
|
t/c w don curtis at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/7/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/7/2008 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/6/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/23/2008 | | 8/4/2008 | | PASS |
|
|
|
plans are approved
|
Case Summary | | | 7/23/2008 | | DONE |
|
|
|
|
Application received | | | 7/23/2008 | | |
|
|
|
|
Pending Assignment by SAM | 7/23/2008 | | | | |
|
|
|
|