Miscellaneous action | | | 5/11/2009 | | DONE |
|
|
|
Plans taken to records to scan
|
INSP-Final Inspection | 3/25/2009 | 3/25/2009 | 3/25/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit was previously finaled by Ken Roule
|
INSP-Alarm Testing | 9/16/2008 | 9/17/2008 | 9/17/2008 | A | PASS |
Troy Cobbley
|
|
|
Vesda testing completed. Test interconnection to main fire alarm panel Also do a full function test to the pre-action system.KR
|
Issue permit | | | 8/12/2008 | | |
|
|
|
|
Plan assigned to (Stephanie) | 7/30/2008 | | 8/11/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Miscellaneous action | | | 8/11/2008 | | DONE |
|
|
|
Recieved a fax indicating a preaction matrix and that it is a double-interlocking system.
|
Alarm Plan Check | | | 8/11/2008 | | PASS |
|
|
|
see comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/11/2008 | | 8/11/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/11/2008 | | DONE |
|
|
|
left vm for dan at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/11/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/7/2008 | | DONE |
|
|
|
Left a message for Dan Buccino regarding the preaction system. In the message, I asked him to fax or email me a matrix showing the preaction system operations as well as indicating if it is double-interlock, non interlock, etc...
|
Application received | | | 7/30/2008 | | |
|
|
|
|