Permit Information
Permit NumberFIR08-00544
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 600 N ROBBINS RD
Project NameIDAHO ELKS REHAB
Customer Number 
ePlanReview 
Description
Revised FIR OH Work Scope:
The contractor resubmitted these revised previously approved plans and calculations to account for changes made in the field during construction. The contractor installed Flex Head arm over connections instead of rigid pipe as originally calculated and approved. Based on the calculations provided, this plan modification does not appear to adversely affect the remote area of operation. This modification has been noted on the plans and dated 09/16/08. FIR OH Work Scope: The Fire Sprinkler scope consists of installing 69 new quick response heads to accommodate a new wall and ceiling layout in the in the Wound Clinic area. The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD08-01101.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  3/11/2009 DONE
Sent for archiving
INSP-Final Inspection12/19/200812/19/200812/19/2008PPASS
DetailsForrest France
C/N items verified for completion, fire sprinkler permit finaled.
INSP-Sprinkler Rough-in/Hydro12/16/200812/16/200812/16/2008PFAIL
DetailsForrest France
Two heads at a meeting room need relocated, one head at a storage room is overspaced, annotated areas on plans approved for cover with today's date.
INSP-Sprinkler Rough-in12/2/200812/3/200812/3/2008PPART
DetailsForrest France
Okay to cover pendent heads at the new entry vestibule, one additional pendent at the reception area soffit also okayed.
INSP-Sprinkler Rough-in11/18/200811/18/200811/18/2008APART
DetailsForrest France
Site verified relocated head at an exam room and one additional head installed at the common corridor vestibule per plans.
INSP-Final Inspection11/14/200811/17/200811/17/2008PPART
DetailsForrest France
Noted correction items finished.
INSP-Final Inspection11/13/200811/14/200811/14/2008AFAIL
DetailsForrest France
Noted obstructed pendent head at exam room 124, missing one head to be added per approved drawings at the hallway vestibule, see locations annotated on stamped plan set.
INSP-Sprinkler Rough-in11/7/200811/10/200811/10/2008PPASS
DetailsTroy Cobbley
See the city approved plans for locations where the sprinkler piping can be covered. It will have todays date and my signature.
INSP-Sprinkler Rough-in/Hydro10/28/200810/28/200810/28/2008APART
DetailsForrest France
OH system modifications approved as noted on plans to date.
INSP-Sprinkler Rough-in10/24/200810/24/200810/24/2008PPART
DetailsForrest France
See city approved plans for areas OK to cover. KR
INSP-Final Inspection9/25/20089/25/20089/25/2008PPART
DetailsForrest France
OH rough-in for the "sleers" area only completed today, circled locations on plans approved for cover, noted one head at the reception counter soffit to be added per drawings, flex-head resubmittals verified.
PLANS/APPL TAKEN TO FRONT DESK  9/25/2008 DONE
DetailsCathy Brown
Inspection Record Card- Fire9/25/2008 9/25/2008 DONE
DetailsCathy Brown
Telephone call  9/25/2008 DONE
DetailsCathy Brown
tlk to jeff already this morning about the permit and fees 8:00 am
Permit Ready to Issue  9/25/2008 DONE
DetailsCathy Brown
CHANGE STATUS TO (ISS)  9/25/2008 DONE
DetailsAlexandra L. DeYoung
Plan assigned to (OutSourced)9/24/2008 9/24/2008 DONE
DetailsCathy Brown
Sprinkler Plan Check9/16/2008 9/23/2008 PASS
Details
These plans were previously approved. This second review of the plan modification and revised calculations affected 14 heads within the remote area of operation. This modification does not appear to adversely affect the remote area of operation.
Bryan Johnson
Plan resubmittals received  9/16/2008 DONE
received 1 letter of transmittal, 5 applications and 5 sets of plans stamped re-submittal and put in fire box
INSP-Sprinkler Rough-in/Hydro9/11/20089/12/20089/12/2008AFAIL
DetailsForrest France
Need to provide documentation addressing the installation of flex type head connections is approved. See item # 13 on the plan review for details. Overhead cover at the drop ceilings is not allowed at this time.
Telephone call  8/14/2008 DONE
Details
t/c w damaris melick at ###-#### - permit ready and fees given
Permit Ready to Issue  8/14/2008 DONE
Details
Issue and Print Permit  8/14/2008 DONE
Inspection Record Card- Fire8/13/2008 8/13/2008 DONE
Details
Sprinkler Plan Check7/31/2008 8/13/2008 PASS
Details
plans are approved
PLANS/APPL TAKEN TO FRONT DESK  8/13/2008 DONE
Details
Application received  7/31/2008  
Pending Assignment by SAM7/31/2008    
Plan assigned to (SAM)7/31/2008