Miscellaneous action | | | 3/11/2009 | | DONE |
|
|
|
Sent for archiving
|
INSP-Final Inspection | 11/26/2008 | 11/28/2008 | 11/28/2008 | A | PASS |
Forrest France
|
|
|
Corrections verified, noted two missing escutcheons to be installed today, permit finaled.
|
INSP-Final Inspection | 11/25/2008 | 11/25/2008 | 11/25/2008 | A | FAIL |
Forrest France
|
|
|
Final pending field tile installation throughout at the drop ceilings
|
INSP-Sprinkler Rough-in | 11/12/2008 | 11/12/2008 | 11/12/2008 | P | PASS |
Troy Cobbley
|
|
|
The second floor sprinkler piping can be covered as marked on the city approved plans with my signature and todays date.
|
INSP-Sprinkler Rough-in | 11/6/2008 | 11/6/2008 | 11/6/2008 | P | DEFR |
Forrest France
|
|
|
Not yet completed for inspection at this time, request intended for 3rd floor permit work.
|
Telephone call | | | 8/27/2008 | | DONE |
|
|
|
t/c w brodie at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/27/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/27/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/27/2008 | | 8/27/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/14/2008 | | 8/26/2008 | | PASS |
|
|
|
plans are approved
|
Application received | | | 8/14/2008 | | |
|
|
|
|
Pending Assignment by SAM | 8/14/2008 | | | | |
|
|
|
|