Miscellaneous action | | | 5/11/2009 | | DONE |
|
|
|
Plans taken to records to scan
|
INSP-Final Inspection | 2/4/2009 | 2/5/2009 | 2/5/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 1/21/2009 | 1/22/2009 | 1/22/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 1/20/2009 | 1/21/2009 | 1/21/2009 | P | FAIL |
Troy Cobbley
|
|
|
The manual pull station is mounted too high. The tamper switch for the PIV had to be adjusted while on site. All other items tested ok.
|
INSP-Sprinkler Rough-in | 1/20/2009 | 1/21/2009 | 1/21/2009 | P | FAIL |
Troy Cobbley
|
|
|
The manual pull station is mounted too high. The tamper switch for the PIV had to be adjusted while on site. All other items tested ok.
|
FIR-Aging Inspection | 11/25/2008 | 11/25/2008 | 11/26/2008 | | NR |
Troy Cobbley
|
|
|
Per Darcy the project is only 50% complete at this time.
|
Alarm Plan Check | | | 8/26/2008 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/26/2008 | | 8/26/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/26/2008 | | DONE |
|
|
|
t/c w darcy holmes at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/26/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/26/2008 | | DONE |
|
|
|
|
Application received | | | 8/21/2008 | | |
|
|
|
|
Plan assigned to (Stephanie) | 8/21/2008 | | 8/21/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|