Miscellaneous action | | | 3/11/2009 | | DONE |
|
|
|
Sent for archiving
|
INSP-Final Inspection | 11/4/2008 | 11/4/2008 | 11/5/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit passed final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2008 | 11/4/2008 | 11/4/2008 | A | PART |
Forrest France
|
|
|
OH fire sprinkler system modifications completed acceptable per the scope of work, noted one leak repaired while on site, one existing non-compliant head at the 2nd floor to be removed prior to final.
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2008 | 11/3/2008 | 11/3/2008 | P | PART |
Forrest France
|
|
|
Okay for cover at the 2nd floor office room ceiling.
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2008 | 10/30/2008 | 10/30/2008 | P | PART |
Forrest France
|
|
|
Sprinkler installation at the 2nd floor hard lid ceiling above the stairway is approved for cover, minor adjustments made while on site, see plans for locations okayed wtih todays date.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2008 | | DONE |
Cathy Brown
|
|
|
|
Override - Parcel Holds | | | 10/30/2008 | | |
|
|
|
|
Inspection Record Card- Fire | 10/30/2008 | | 10/30/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 10/30/2008 | | DONE |
Cathy Brown
|
|
|
lft vm with gerald ebeling ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/30/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 10/30/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Sprinkler Plan Check | 10/21/2008 | | 10/28/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Telephone call | | | 10/21/2008 | | DONE |
|
|
|
Telcon from Brett, ESI, requesting approval to pay B. Johnson to expedite the plan modifications plans they submitted today. I explained that in order to maintain equitable service to all customers, we do not allow contractors to pay our plan reviewers on the side, to expedite their plans. I also explained we have 2 plans which are 2 days beyond our standard 10-day review period, as well as 7 other plans in line, which we need to serve fairly. I indicated we would certainly review their plans as soon as possible, and if the work load allows, it will be done in less than the 2-week standard.
|
Plan resubmittals received | | | 10/21/2008 | | |
Barbara Stitt
|
|
|
|
Telephone call | | | 9/23/2008 | | DONE |
|
|
|
Telcon from Gerald Eberling, DeBest (###-####) requesting a meeting with the City to discuss possible re-design options which would not require hydraulic calculations. I declined, since our AHJ authority is only to approve plans for Code compliance, not to make design recommendation.. He indicated they now have plans of the existing system, but the owner did not want to pay DeBest to input the existing system data into their calc program and run the calculations. I suggested if they could show the modified area is upstream of the originally calc'd most remote area, and they are only adding additional gridded mains which would improve the hydraulic performance of the most remote area, it might be possible to only calc the modified area back to the riser, and avoid recalculating the entire system again. He indicated he would investigate possibility and call me back.
|
Sprinkler Plan Check | 8/22/2008 | | 8/28/2008 | | FAIL |
|
|
|
These plans were denied due to a sprinkler head listing discrepancy. Upon request the denied set of plans may be received from my office for salvage. The denied set of plans will be maintained for 5 working days.
Bryan Johnson
|
Application received | | | 8/22/2008 | | |
|
|
|
|
Pending Assignment by SAM | 8/22/2008 | | | | |
Sam Rogers
|
|
|
Outsouced to johnson Consulting.
|