INSP-Final Inspection | 4/22/2009 | 4/23/2009 | 4/23/2009 | A | PASS |
Forrest France
|
|
|
Final inspection passed, one missing escutcheon installed while on site, permit finaled.
|
INSP-Conference | 4/22/2009 | 4/22/2009 | 4/22/2009 | P | DONE |
Forrest France
|
|
|
Regarding project related fire alarm permit and final inspection schedule.
|
INSP-Sprinkler Rough-in | 10/21/2008 | 10/22/2008 | 10/22/2008 | A | PART |
Forrest France
|
|
|
Tenting at the attic area wet system piping is acceptable, two exposed locations repaired while on site. NOTE: Supply line flushing also completed today, discussed items needed for permit final.
|
INSP-Sprinkler Rough-in | 10/20/2008 | 10/21/2008 | 10/21/2008 | P | PART |
Forrest France
|
|
|
Rough in inspection passed, two missing hangers added while on site, need inspection for tenting when complete, riser is not yet finished, noted heads not installed at some locations.
|
Issue and Print Permit | | | 9/29/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/26/2008 | | 9/26/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/5/2008 | | 9/26/2008 | | PASS |
|
|
|
plans are approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2008 | | DONE |
|
|
|
|
Telephone call | | | 9/26/2008 | | DONE |
Cathy Brown
|
|
|
lft vm with john edes ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 9/26/2008 | | DONE |
|
|
|
|
Application received | | | 9/5/2008 | | |
|
|
|
|
Pending Assignment by SAM | 9/5/2008 | | | | |
|
|
|
|