INSP-Final Inspection | 3/12/2009 | 3/12/2009 | 3/12/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 11/4/2008 | 11/5/2008 | 11/5/2008 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed. The water flow seemed low but there was a long run of hose. I will verify water supply during forward flush.
|
INSP-Sprinkler Rough-in/Hydro | 11/4/2008 | 11/5/2008 | 11/5/2008 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2008 | 10/31/2008 | 10/31/2008 | A | FAIL |
Troy Cobbley
|
|
|
The underground hydro test failed.
|
INSP-Sprinkler Rough-in | 10/17/2008 | 10/17/2008 | 10/17/2008 | P | PASS |
Troy Cobbley
|
|
|
Per Mark Senteno the PIV is ok to be located approximately 12' from the building. The remaining underground piping can be covered. I let the general contractor know that it would be a good idea to install conduit in the trench prior to bury for the monitoring of the tamper switch.
|
INSP-Sprinkler Rough-in | 10/14/2008 | 10/15/2008 | 10/15/2008 | A | FAIL |
Troy Cobbley
|
|
|
The PIV is located 12' from the building not the required 40'. The approved plans show 40'. Relocate the PIV or get fire dept approval for the new location.
|
INSP-Sprinkler Rough-in/Hydro | 9/16/2008 | 9/16/2008 | 9/16/2008 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was for just the 12'-0" of 6" stub-out. This underground piping is ok to bury.
|
Sprinkler Plan Check | 9/9/2008 | | 9/15/2008 | | PASS |
|
|
|
These plans were approved with conditions. An additional hydrant appears to be required. Plans are approved w/conditions by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 9/15/2008 | | DONE |
Cathy Brown
|
|
|
tlk to jeff anderson ###-#### that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 9/15/2008 | | 9/15/2008 | | DONE |
Cathy Brown
|
|
|
|
Permit Ready to Issue | | | 9/15/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 9/15/2008 | | DONE |
|
|
|
|
Application received | | | 9/9/2008 | | |
|
|
|
|
Pending Assignment by SAM | 9/9/2008 | | | | |
Sam Rogers
|
|
|
|