Sprinkler Plan Check | 9/9/2008 | | 9/23/2009 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Miscellaneous action | | | 3/11/2009 | | DONE |
|
|
|
Sent for archiving
|
INSP-Final Inspection | 1/13/2009 | 1/13/2009 | 1/13/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 1/5/2009 | 1/6/2009 | 1/6/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas inspected today on the second floor where the piping can be covered.
|
INSP-Sprinkler Rough-in | 12/17/2008 | 12/17/2008 | 12/17/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the location on the second floor where the sprinkler piping is ok to cover.
|
INSP-Final Inspection | 11/10/2008 | 11/10/2008 | 11/10/2008 | P | PART |
Troy Cobbley
|
|
|
The sprinklers in the second floor south pod are passed
|
INSP-Final Inspection | 11/10/2008 | 11/10/2008 | 11/10/2008 | P | CANC |
Troy Cobbley
|
|
|
Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Final Inspection | 11/10/2008 | 11/10/2008 | 11/10/2008 | P | CANC |
Troy Cobbley
|
|
|
Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Sprinkler Rough-in | 10/21/2008 | 10/21/2008 | 10/21/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping is ok to cover.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/23/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 9/23/2008 | | 9/23/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 9/23/2008 | | DONE |
Cathy Brown
|
|
|
tlk to brodie at ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 9/23/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 9/23/2008 | | DONE |
|
|
|
|
Application received | | | 9/9/2008 | | |
|
|
|
|
Pending Assignment by SAM | 9/9/2008 | | | | |
Sam Rogers
|
|
|
|