INSP-Final Inspection | 8/18/2009 | 8/19/2009 | 8/19/2009 | A | PASS |
Forrest France
|
|
|
Underground fire supply line permit work approved for final status.
|
INSP-Sprinkler Rough-in/Hydro | 3/23/2009 | 3/23/2009 | 3/23/2009 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic testing completed satisfactory. Supply line flush also completed okay post hydro test.
|
INSP-Sprinkler Rough-in | 9/29/2008 | 9/30/2008 | 9/30/2008 | P | PASS |
Forrest France
|
|
|
Underground OK to cover. KR
|
Issue and Print Permit | | | 9/15/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/11/2008 | | 9/11/2008 | | PASS |
Scott Arellano
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/11/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/11/2008 | | 9/11/2008 | | DONE |
|
|
|
|
Telephone call | | | 9/11/2008 | | DONE |
|
|
|
t/c w greg johnson at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 9/11/2008 | | DONE |
|
|
|
|
Application received | | | 9/10/2008 | | |
|
|
|
|
Pending Assignment by SAM | 9/10/2008 | | | | |
|
|
|
|