Miscellaneous action | | | 5/11/2009 | | DONE |
|
|
|
Plans taken to records to scan
|
INSP-Final Inspection | 1/14/2009 | 1/16/2009 | 1/16/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. The elevator interconnect was tested with the state elevator inspector.
|
INSP-Final Inspection | 1/13/2009 | 1/14/2009 | 1/14/2009 | A | FAIL |
Troy Cobbley
|
|
|
Just need the elevator interconnects with the facp to be tested.
|
INSP-Final Inspection | 1/7/2009 | 1/8/2009 | 1/8/2009 | A | FAIL |
Troy Cobbley
|
|
|
All of the initiating devices were tested today. Items needing corrected include providing separate points for the first floor flow switch and the second floor flow switch. The horn/strobes need to be tested for sync and all of the elevator functions need to be tested as well. Permit will not be finaled until Alarmco has submitted and passed inspection for their wireless transmitter. As-builts from Simplex are required showing the small modifications and the deletion of the phone lines.
|
INSP-Final Inspection | 1/7/2009 | 1/7/2009 | 1/8/2009 | P | FAIL |
Troy Cobbley
|
|
|
No inspection was performed due to time constraints and the new facp is not utilizing the phone lines as per the approved drawings. It is using a wireless transmitter that has been installed by Alarmco. Alarmco will need to submitt a separate permit for approval to use this device.
|
FIR-Aging Inspection | 12/23/2008 | 12/23/2008 | 12/23/2008 | | DONE |
Forrest France
|
|
|
Under construction, work in progress.
|
Inspection Record Card- Fire | 9/23/2008 | | 9/23/2008 | | DONE |
|
|
|
|
Telephone call | | | 9/23/2008 | | DONE |
|
|
|
left message w laura for charlie bayne at ###-#### - permit ready and no fees due (new building)
|
Permit Ready to Issue | | | 9/23/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/23/2008 | | DONE |
|
|
|
|
Alarm Plan Check | | | 9/22/2008 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/2008 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2008 | | |
|
|
|
gave plans to charlie with simplex grinnell
|
Plan assigned to (Stephanie) | 9/19/2008 | | 9/19/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan resubmittals received | | | 9/19/2008 | | |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | | | 9/16/2008 | | FAIL |
|
|
|
Please see redlined drawings and review comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/16/2008 | | DONE |
|
|
|
denied plans are available for pick up at the permit desk
|
Miscellaneous action | | | 9/16/2008 | | DONE |
|
|
|
Faxed review comments to contractor
|
Application received | | | 9/10/2008 | | |
|
|
|
|
Plan assigned to (Stephanie) | 9/10/2008 | | 9/10/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Case Summary | | | 9/10/2008 | | DONE |
|
|
|
|