Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberFIR08-00640
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 3236 E AMITY RD
Project NameMAACO
Customer Number 
ePlanReview 
Description
Automatic Fire Sprinkler System Requirements: Spray booths and spray rooms shall be protected by an approved automatic fire-extinguishing system complying with Chapter 9. Protection shall also extend to exhaust plenums, exhaust ducts and both sides of dry filters when such filters are used. A permit is required for this work, as noted above. (Ref. IFC 1504.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/8/200810/9/200810/9/2008APASS
DetailsTroy Cobbley
Paint booth fire sprinkler permit finaled. KR
INSP-Sprinkler Rough-in/Hydro10/8/200810/8/200810/8/2008PDONE
DetailsTroy Cobbley
Fire sprinkler system booth protection competed. Permit needs to be called in for final inspection. KR.
INSP-Sprinkler Rough-in/Hydro10/6/200810/7/200810/7/2008ANR
DetailsForrest France
bruce Phone #: ###-#### Inspection to be rescheduled per conversation with contractor.
Override - Parcel Holds10/6/20081/1/190010/6/2008  
hydro inspection
Override - Parcel Holds  10/1/2008  
Issue and Print Permit  10/1/2008 DONE
DetailsAlexandra L. DeYoung
Override - Parcel Holds  9/30/2008  
Inspection Record Card- Fire9/30/2008 9/30/2008 DONE
Details
Sprinkler Plan Check9/16/2008 9/30/2008 PASS
Details
plans are approved w conditions
PLANS/APPL TAKEN TO FRONT DESK  9/30/2008 DONE
Details
Telephone call  9/30/2008 DONE
Details
t/c w brook nelson at ###-#### - permit ready and fees given
Override - Parcel Holds  9/30/2008  
Permit Ready to Issue  9/30/2008 DONE
Details
Miscellaneous action  9/24/2008 DONE
Had this permit re-attached to the TI permit BLD08-00609; application erroneously showed it to be attached to the shell permit (BLD08-00395)
Early Start  9/18/2008 FAIL
Early Start request denied. (DOC attached). The following email was sent 9/18/08
Brook,
The intent of early start permits is allow limited installation, to accommodate critical construction project schedules, where there is a delay in our normal permit processing times or an unexpected critical construction coordination issue. It is not intended to allow across the board approvals for installation without approved plans. In this particular case, there appears to be no other construction permits associated with this sprinkler permit, the permit application was only received two days ago, and we do not anticipate any delays in the review process. Therefore, I must respectfully decline to approve your request at this time.
Regards,
Sam
Application received  9/16/2008  
Pending Assignment by SAM9/16/2008