Miscellaneous action | | | 1/5/2010 | | DONE |
Tim Frost
|
|
|
Drawings sent for scanning.
|
INSP-Final Inspection | 10/20/2009 | 10/20/2009 | 10/20/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
Pending Assignment by SAM | 9/18/2008 | | 6/4/2009 | | DONE |
Tim Frost
|
|
|
6/4/2009 13:53:25 TRF - activity updated through activity FIRA158 from case FIR08-00830.
|
INSP-Supply line flush | 12/4/2008 | 12/5/2008 | 12/5/2008 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 12/2/2008 | 12/3/2008 | 12/3/2008 | A | PASS |
Troy Cobbley
|
|
|
underground hydro test passed for both the supply and the FDC
|
INSP-Sprinkler Rough-in/Hydro | 11/11/2008 | 11/12/2008 | 11/12/2008 | A | PASS |
Troy Cobbley
|
|
|
The underground sprinkler piping can be covered.
|
Plan resubmittals received | | | 11/6/2008 | | DONE |
Cathy Brown
|
|
|
|
Plan assigned to (Scott) | 11/6/2008 | | 11/6/2008 | | PASS |
Scott Arellano
|
|
|
Routing the FDC to the Cloverdale side of the building.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/6/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/6/2008 | | 11/6/2008 | | DONE |
|
|
|
|
Telephone call | | | 11/6/2008 | | DONE |
|
|
|
t/c w jeff anderson at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 11/6/2008 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/6/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
(F) Reprint permit | | | 11/6/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Telephone call | | | 10/21/2008 | | DONE |
|
|
|
Telcon from Bryan, at Colson & Colson (GC), asking the max. distance of FDC from Fire hydrants. He incidentally mentioned the FDC was shown on civil drwg as a yard FDC along Cloverdale but sprinkler plan shows it on the north wall of the bldg. I subsequently reviewed the building permit Fire review comments and the sprinker plans. The location shown on sprinkler plans does not meet the Fire Code review comment #34, requiring the FDC to be on the street side of the building, clearly visible and discernable from the street. I called Jeff Anderson, TVFP, and explained that we need the FDC to be piped to the exterior side facing Coverdale street. It can be a yard FDC or wall-mounted FDC (except not located in the narrow recessed area which would not be clearly discernable). He agreed to advise the architect and make the change in FDC location.
|
Case Summary | | | 10/21/2008 | | |
|
|
|
|
Issue and Print Permit | | | 10/2/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/18/2008 | | 10/1/2008 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 10/1/2008 | | 10/1/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 10/1/2008 | | DONE |
Cathy Brown
|
|
|
tlk to jeff anderson ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/1/2008 | | DONE |
Cathy Brown
|
|
|
|
Application received | | | 9/18/2008 | | |
|
|
|
|