Permit Information
Permit NumberFIR08-00675
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 1072 N LIBERTY ST
Project NameST ALPHONSUS-MOB #7
Customer Number 
ePlanReview 
Description
FIR Scope UG: Beginning from an existing tapping tee and valve of an 8” supply (Circulating Loop) in the street ( Hartman), run 130’-0” of 8” C-900 out and rise up into a riser room on the North end of the bldg. All work shall be performed in accordance with NFPA 24 & 13.
FIR Scope OH Shell Only: Beginning from the 8” flanged supply located on the first floor riser room; install a complete 4” wet pipe riser to supply the sprinkler system through out this three story bldg. including a mechanical pent house, and a combination Manual Class I Wet Standpipe.
The fire sprinkler work shall comply with NFPA 13& 14 2007, NFPA 24-2002 the IFC-2006.
The fire sprinkler system work shall comply with IFC 2006, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to permit BLD08-01210.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/21/20095/21/20095/21/2009PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro5/19/20095/19/20095/19/2009PCANC
DetailsTroy Cobbley
Canceled due to the project related fire alarm system/permit not being complete. The backflow preventor has been certified. The fire alarm interconnections need to be tested/verified for final.
Meeting  5/19/2009 DONE
Details
Per the Fire Marshal (Mark Senteno) the final stand pipe flow test, at the most remote location, will be considered acceptable without the presence of the fire department pumper apparatus. SJA
INSP-Final Inspection5/14/20095/18/20095/18/2009AFAIL
DetailsTroy Cobbley
Forward flush passed. Project was not finaled due to the fire alarm permit was not ready for inspection and questions regarding the standpipe flow as per note 42 of the review comments was an issue. Also the backflow preventor needs to be certified.
INSP-Sprinkler Rough-in4/8/20094/8/20094/8/2009PPASS
DetailsTroy Cobbley
The second and third floor sprinkler rough-in passed.
INSP-Sprinkler Rough-in/Hydro4/7/20094/8/20094/8/2009APASS
DetailsTroy Cobbley
The overhead hydro test passed.
INSP-Sprinkler Rough-in3/9/20093/9/20093/9/2009PPASS
DetailsTroy Cobbley
The sprinkler piping above the ceiling in the third floor central stair tower is ok to cover.
INSP-Supply line flush3/4/20093/9/20093/9/2009PPASS
DetailsTroy Cobbley
The underground flush passed.
INSP-Sprinkler Rough-in/Hydro3/3/20093/4/20093/4/2009PCANC
DetailsTroy Cobbley
UG Hydro Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley
INSP-Sprinkler Rough-in/Hydro3/2/20093/3/20093/4/2009PPART
DetailsTroy Cobbley
UG Hydro passed. The rough-in inspection of the first and second floors did not pass. The problem is alot of pendant heads were designed to be installed under duct work and they ended up not being installed under the duct work and/or the duct work has been moved. The heads now exceed 22" from the deck. The pipe size, hangers and earthquaking is ok. The third floor, standpipes and riser has not been inspected.
INSP-Sprinkler Rough-in/Hydro12/12/200812/12/200812/12/2008PCANC
DetailsTroy Cobbley
UG Hydro Test - Contact: Dave Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley
INSP-Supply line flush12/10/200812/11/200812/11/2008PCANC
DetailsTroy Cobbley
This was for a hydro test and is to be cancelled per Dave.
INSP-Sprinkler Rough-in10/27/200810/27/200810/28/2008PPASS
DetailsTroy Cobbley
The underground supply piping is ok to cover and has been installed per plan.
Issue and Print Permit  10/20/2008 DONE
DetailsAlexandra L. DeYoung
PLANS/APPL TAKEN TO FRONT DESK  10/17/2008 DONE
DetailsCathy Brown
Inspection Record Card- Fire10/17/2008 10/17/2008 DONE
DetailsCathy Brown
Telephone call  10/17/2008 DONE
DetailsCathy Brown
lft ms with randy bowron ###-#### ext 244 that permit and fees area ready to be picked up
Permit Ready to Issue  10/17/2008 DONE
DetailsCathy Brown
Sprinkler Plan Check10/2/2008 10/16/2008 PASS
Details
Plans are approved by Bryan Johnson
Application received  10/2/2008  
Pending Assignment by SAM10/2/2008