Miscellaneous action | | | 5/11/2009 | | DONE |
|
|
|
Plans taken to records to scan
|
INSP-Final Inspection | 3/6/2009 | 3/6/2009 | 3/6/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Final Inspection | 3/4/2009 | 3/5/2009 | 3/5/2009 | A | FAIL |
Troy Cobbley
|
|
|
Provide as-builts showing the relocated smoke detectors, relocated NAC panel and the facp interconnection with the hvac shutdown.
|
INSP-Final Inspection | 3/2/2009 | 3/3/2009 | 3/3/2009 | A | FAIL |
Troy Cobbley
|
|
|
No inspection was performed due to the city approved plans not being on site. I did check the strobe candella, spacing and heights while I was there and found no problems.
|
FIR-Aging Inspection | 1/22/2009 | 1/22/2009 | 1/27/2009 | | NR |
Troy Cobbley
|
|
|
Work is still in progress per dave
|
Alarm Plan Check | | | 10/21/2008 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/21/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/21/2008 | | 10/21/2008 | | DONE |
|
|
|
|
Telephone call | | | 10/21/2008 | | DONE |
|
|
|
left message w trisha for monty at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/21/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/21/2008 | | DONE |
|
|
|
|
Application received | | | 10/6/2008 | | |
|
|
|
|
Plan assigned to (Stephanie) | 10/6/2008 | | 10/6/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Case Summary | | | 10/6/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|