INSP-Final Inspection | 6/9/2009 | 6/9/2009 | 6/9/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 6/5/2009 | 6/8/2009 | 6/8/2009 | A | CANC |
Troy Cobbley
|
|
|
The fire alarm system was not reading for testing.
|
INSP-Final Inspection | 6/5/2009 | 6/5/2009 | 6/5/2009 | P | FAIL |
Troy Cobbley
|
|
|
The interconnections with the fire alarm system could not be tested. The forward flow of the backflow preventor passed.
|
Plan assigned to (Tim) | 5/13/2009 | | 5/15/2009 | | DONE |
Tim Frost
|
|
|
5/15/2009 11:06:18 TRF - activity updated through activity FIRA22 from case FIR08-00706.
|
Sprinkler Plan Check | 5/15/2009 | | 5/15/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
This was a plan modification review. Only clouded areas were reviewed.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/15/2009 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 5/15/2009 | | 5/15/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Telephone call | | | 5/15/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
permit ready, fees given
|
Permit Ready to Issue | | | 5/15/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Issue and Print Permit | | | 5/15/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/13/2009 | | DONE |
|
|
|
received 3 sets of resubmitted apps & plans sent to fire(Tim Frost)
|
Pending Assignment by SAM | 10/16/2008 | | 5/13/2009 | | DONE |
Sam Rogers
|
|
|
5/13/2009 11:36:22 RAD - activity updated through activity FIRA158 from case FIR08-00706.
|
Pending Assignment by SAM | 11/24/2008 | | 5/13/2009 | | DONE |
Sam Rogers
|
|
|
5/13/2009 11:36:22 RAD - activity updated through activity FIRA158 from case FIR08-00706.
|
INSP-Sprinkler Rough-in | 4/10/2009 | 4/13/2009 | 4/13/2009 | A | PART |
Troy Cobbley
|
|
|
The sprinkler piping can be covered. See the city approved plans for the locations of three items that need corrected such as a blocked head, painted head and an overspaced head. Also there is no computer record of the plans being resubmitted due to a sprinkler main being modified/relocated in a remote area and theFDCbeing relocated. See the previous inspection entry for these items.
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2009 | 4/10/2009 | 4/10/2009 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed
|
INSP-Sprinkler Rough-in | 1/26/2009 | 1/26/2009 | 1/26/2009 | P | PART |
Troy Cobbley
|
|
|
The sprinkler rough-in is passed. Not all of the sprinkler drops have been installed. Final sprinkler spacing will need to be verified when drops, ceilings and soffits have been installed. The FDC has been relocated and a sprinkler main in a hydraulic remote area on the north side of the building has been rerouted. These changes will need to be verified by teh plan reviewer.
|
(F) Reprint permit | | | 12/5/2008 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/5/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/24/2008 | | 12/2/2008 | | PASS |
|
|
|
Note: This was the third review of these plans. Twelve heads in the remote area 3 were affected as a result of this resubmittal. Plans & Calculations are Approved by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/2/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 12/2/2008 | | 12/2/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 12/2/2008 | | DONE |
Cathy Brown
|
|
|
tlk to lillie ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 12/2/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/24/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/17/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 11/17/2008 | | 11/17/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 11/17/2008 | | DONE |
Cathy Brown
|
|
|
lft ms with reception for lillie ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 11/17/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/17/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/7/2008 | | 11/12/2008 | | PASS |
|
|
|
Plans & Calculations are approved by Bryan Johnson
|
Plan resubmittals received | | | 11/7/2008 | | |
|
|
|
Rec'd plan mod, five copies of application, five copies of submittal packet, and five copies of sheets FP1, FP2, and FP3; taken to fire review
|
Sprinkler Plan Check | 10/16/2008 | | 10/29/2008 | | FAIL |
|
|
|
These plans were denied due to lack of or incorrect information provided. The contractor has elected to retrieve the denied set of plans from my office for salvage.
|
Application received | | | 10/16/2008 | | |
|
|
|
|
Case Summary | | | 10/16/2008 | | |
|
|
|
|