Miscellaneous action | | | 5/11/2009 | | DONE |
|
|
|
Plans taken to records to scan
|
INSP-Final Inspection | 4/2/2009 | 4/2/2009 | 4/2/2009 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 3/31/2009 | 4/2/2009 | 4/2/2009 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/12/2009 | 3/12/2009 | 3/12/2009 | P | FAIL |
Troy Cobbley
|
|
|
Provide an updated map at the facp and the releasing panel, provide another isolating module in the new building for lightning protection and modify the system so that the central station recieves supervisory signals instead of trouble signals on zone 32.
|
FIR-Aging Inspection | 2/2/2009 | 2/2/2009 | 2/5/2009 | | DONE |
Troy Cobbley
|
|
|
Work is in progress.
|
Inspection Record Card- Fire | 11/3/2008 | | 11/3/2008 | | DONE |
|
|
|
|
Telephone call | | | 11/3/2008 | | DONE |
|
|
|
t/c w robert king at ###-#### - permit ready and no fee
|
Permit Ready to Issue | | | 11/3/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/3/2008 | | DONE |
|
|
|
|
Alarm Plan Check | | | 10/31/2008 | | PASS |
|
|
|
See review comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2008 | | DONE |
|
|
|
|
Application received | | | 10/21/2008 | | |
|
|
|
|
Plan assigned to (Stephanie) | 10/21/2008 | | 10/21/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Case Summary | | | 10/21/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|