INSP-Final Inspection | 7/9/2009 | 7/9/2009 | 7/9/2009 | A | PASS |
Forrest France
|
|
|
Correction items verified for completion, fire sprinkler permit finaled.
|
INSP-Final Inspection | 4/20/2009 | 4/21/2009 | 4/21/2009 | A | PART |
Forrest France
|
|
|
New dry system trip testing completed satisfactory, still missing two upright heads at the generator room.
|
INSP-Sprinkler Rough-in/Hydro | 4/17/2009 | 4/17/2009 | 4/17/2009 | P | PART |
Forrest France
|
|
|
Noted two upright heads at the generator room not yet installed.
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2009 | 4/8/2009 | 4/8/2009 | A | PART |
Forrest France
|
|
|
Concluded satisfactory 24 hour air test for the new dry system.
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2009 | 4/7/2009 | 4/7/2009 | P | PART |
Forrest France
|
|
|
Begin 24 hr. air testing at 11:00 AM @ 40psi.
|
INSP-Sprinkler Rough-in/Hydro | 4/2/2009 | 4/2/2009 | 4/2/2009 | P | PART |
Forrest France
|
|
|
New dry system piping hydrostatic test completed, discussed schedule for 24 hr. air testing next week.
|
INSP-Sprinkler Rough-in/Hydro | 3/5/2009 | 3/5/2009 | 3/5/2009 | P | NR |
Forrest France
|
|
|
Don Phone#: ###-#### Not ready per phone call from contractor
|
INSP-Sprinkler Rough-in/Hydro | 3/3/2009 | 3/4/2009 | 3/3/2009 | A | DEFR |
Forrest France
|
|
|
Don Phone #: ###-####
|
INSP-Sprinkler Rough-in | 1/16/2009 | 1/20/2009 | 1/21/2009 | A | FAIL |
Forrest France
|
|
|
Noted 1/2" upright heads have been installed where approved plans and submittals indicate 3/4" to be used.
|
INSP-Sprinkler Rough-in/Hydro | 1/21/2009 | 1/21/2009 | 1/21/2009 | A | PART |
Forrest France
|
|
|
New 2" steel pipe and branchline outlets above the sheetrock ceiling at the UPS room are okay for cover.
|
Sprinkler Plan Check | 10/28/2008 | | 11/12/2008 | | PASS |
|
|
|
Plans & Calculations are approved by Bryan Johnson
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2008 | | DONE |
Cathy Brown
|
|
|
|
Inspection Record Card- Fire | 11/12/2008 | | 11/12/2008 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 11/12/2008 | | DONE |
Cathy Brown
|
|
|
lft vm with brodie ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 11/12/2008 | | DONE |
Cathy Brown
|
|
|
|
Issue and Print Permit | | | 11/12/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Application received | | | 10/28/2008 | | |
|
|
|
|
Pending Assignment by SAM | 10/28/2008 | | | | |
|
|
|
|