INSP-Final Inspection | 12/3/2008 | 12/3/2008 | 12/3/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 11/7/2008 | 11/7/2008 | 11/7/2008 | P | PART |
Forrest France
|
|
|
OH fire sprinkler rough-in is acceptable, noted items repaired.
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2008 | 11/6/2008 | 11/6/2008 | P | PART |
Forrest France
|
|
|
New piping and heads at the sheetrock ceilings are okay for cover, noted two existing upright heads in need of replacement due to paint on the elements and frames.
|
Plan resubmittals received | | | 11/5/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/5/2008 | | 11/5/2008 | | PASS |
Scott Arellano
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/5/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/5/2008 | | 11/5/2008 | | DONE |
|
|
|
|
Telephone call | | | 11/5/2008 | | DONE |
|
|
|
t/c w john at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 11/5/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/5/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/3/2008 | | 11/3/2008 | | FAIL |
Scott Arellano
|
|
|
Application submittal package incmoplete. Manufacturers cut sheet for new sprinkler heads not submitted. faxed resubmittal item to applicant.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2008 | | |
|
|
|
|
Application received | | | 10/31/2008 | | |
|
|
|
|
Pending Assignment by SAM | 10/31/2008 | | | | |
|
|
|
|