INSP-Final Inspection | 8/20/2009 | 8/20/2009 | 8/21/2009 | P | PASS |
Forrest France
|
|
|
Underground fire supply line permit work approved for final status.
|
INSP-Supply line flush | 4/3/2009 | 4/6/2009 | 4/6/2009 | A | PASS |
Forrest France
|
|
|
Completed UG supply line flush for system leads to the truck return building and maintenance building.
|
Sprinkler Plan Check | 4/3/2009 | | 4/3/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2009 | | DONE |
|
|
|
|
Telephone call | | | 4/3/2009 | | DONE |
|
|
|
left vm for jeff anderson ###-#### - permit (resubmittal) is ready to be picked and no fee
|
Permit Ready to Issue | | | 4/3/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/3/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/3/2009 | | DONE |
Barbara Stitt
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 4/2/2009 | 4/2/2009 | 4/2/2009 | A | PART |
Forrest France
|
|
|
See dated plan notes for UG installation work okayed.
|
INSP-Sprinkler Rough-in/Hydro | 3/31/2009 | 4/1/2009 | 4/1/2009 | P | PART |
Forrest France
|
|
|
Hydrostatic testing for UG supply lead in piping service to the truck return and maintenance buildings each completed satisfactory, maint. building service okayed within allowable leakage amounts per NFPA 13.
|
INSP-Sprinkler Rough-in | 3/31/2009 | 3/31/2009 | 3/31/2009 | A | PART |
Forrest France
|
|
|
Thrust blocking at the truck return building supply line okayed.
|
INSP-Supply line flush | 3/27/2009 | 3/30/2009 | 3/30/2009 | P | PART |
Forrest France
|
|
|
See initials on plans for the last riser supply lead-in flush completed today serving the main building.
|
INSP-Sprinkler Rough-in | 3/30/2009 | 3/30/2009 | 3/30/2009 | P | FAIL |
Forrest France
|
|
|
Thrust blocks at two 45 ells in the supply line to the SE detatched building are not of sufficient size or location, field changes in pipe routes must be shown on approved plans.
|
INSP-Supply line flush | 3/27/2009 | 3/30/2009 | 3/30/2009 | A | PART |
Forrest France
|
|
|
UG fire supply line flush for two east side riser lead-ins completed okay.
|
INSP-Supply line flush | 3/27/2009 | 3/27/2009 | 3/27/2009 | P | PASS |
Troy Cobbley
|
|
|
The south facing stub-in, located second from the east end, passed the underground flush.
|
INSP-Supply line flush | 3/26/2009 | 3/27/2009 | 3/27/2009 | A | PART |
Forrest France
|
|
|
UG fire supply line flush for the east half building service completed satisfactory, also flushed lead in to the SE corner riser. See approved plans for marked locations with today's date.
|
INSP-Sprinkler Rough-in/Hydro | 3/26/2009 | 3/26/2009 | 3/27/2009 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test for the east half of the building service passed- see marked area on approved plan set.
|
INSP-Supply line flush | 3/19/2009 | 3/19/2009 | 3/19/2009 | A | PART |
Forrest France
|
|
|
UG lead in flush for the 3rd to west riser as marked on approved plans completed okay.
|
INSP-Supply line flush | 3/16/2009 | 3/18/2009 | 3/18/2009 | A | PART |
Forrest France
|
|
|
UG flush completed satisfactory for the two far west system lead-ins, ( main supply line and the west main supply line included).
|
INSP-Sprinkler Rough-in/Hydro | 3/16/2009 | 3/17/2009 | 3/17/2009 | P | NR |
Forrest France
|
|
|
Brian Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 3/13/2009 | 3/16/2009 | 3/16/2009 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic testing for the lead in to the pump house and the supply/feed to the west half of the building including three stubs passed within allowable leakage amounts per NFPA 13.
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2009 | 3/11/2009 | 3/11/2009 | A | NR |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 3/10/2009 at 12:59:03 PM. Contact: ###-####. NOTE: Hydrostatic test not ready per phone call from contractor.
|
INSP-Sprinkler Rough-in/Hydro | 3/3/2009 | 3/4/2009 | 3/4/2009 | P | PASS |
Troy Cobbley
|
|
|
See the onsite plans for the locations inspected today.
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2009 | 3/3/2009 | 3/3/2009 | A | PART |
Forrest France
|
|
|
See approved plan set for locations of three thrust blocks at tee's feeding system risers okayed for cover marked with today's date.
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2009 | 3/2/2009 | 3/3/2009 | P | PART |
Forrest France
|
|
|
Verified thrust blocking at 45's adjacent to the storm drain at the Freight street entrance.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2009 | 2/25/2009 | 2/25/2009 | A | PASS |
Troy Cobbley
|
|
|
This was a cover inspection at multiple areas of the underground supply piping. See the city approved plans for locations where the piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/20/2009 | 2/24/2009 | 2/24/2009 | P | CANC |
Troy Cobbley
|
|
|
This is for cover inspection at 12" site feed at jobsite entrance and south center 12" near main bldg. Please call with time frame. Thank you Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 2/18/2009 | 2/19/2009 | 2/19/2009 | A | PART |
Forrest France
|
|
|
See approved plans for underground fire supply line pipe runs okayed for cover, added 45's for change in bury depth below the storm drain adjacent to Freight Street to be indicated on as-builts, also need to verify thrust blocking/deadmans at top 45's prior to cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/18/2009 | 2/18/2009 | 2/18/2009 | P | DEFR |
Forrest France
|
|
|
This is for cover inspection at 12" site feed at jobsite entrance. Thrust blocks will be ready at 1:00 pm. If inspection does not fit schedule please disregard and complete tomorrow am. Thank you. Phone #: ###-#### Internet Inspection Request from: Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 2/13/2009 | 2/13/2009 | 2/17/2009 | P | PART |
Forrest France
|
|
|
See approved plans for locations okay for bury.
|
INSP-Sprinkler Rough-in/Hydro | 2/12/2009 | 2/12/2009 | 2/12/2009 | P | NR |
Forrest France
|
|
|
Missing thrust blocks, seismic clearance at the riser SW corner is not sufficient, bolts at mech. tees and 90's need coated and covered.
|
INSP-Sprinkler Rough-in/Hydro | 2/4/2009 | 2/9/2009 | 2/7/2009 | P | CANC |
Forrest France
|
|
|
Please call for time frame. This is cover inspection for underground. Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 2/4/2009 | 2/5/2009 | 2/4/2009 | P | CANC |
Forrest France
|
|
|
Please call with time frame for inspection. This is for undergound cover inspection at South East area of site. Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Sprinkler Rough-in | 2/2/2009 | 2/4/2009 | 2/4/2009 | A | PART |
Forrest France
|
|
|
Ductile riser and stub out connection to the yard PIV at the NE corner of the building okayed for cover, discussed bedding material install, noted PIV final adjustment to be provided at 3' above finish grade when complete, see stamped plan set for initials and location of work inspected today.
|
INSP-Sprinkler Rough-in/Hydro | 2/1/2009 | 2/3/2009 | 2/3/2009 | A | NR |
Forrest France
|
|
|
Work underway for the portion of piping to be inspected-missing one 90, thrustblocks, etc., not ready at this time. Discussed AM inspection scheduled 2/4.
|
INSP-Sprinkler Rough-in/Hydro | 2/1/2009 | 2/2/2009 | 2/2/2009 | P | CANC |
Forrest France
|
|
|
Cover inspection for portion of undergground. Please call and inform of time frame. Phone #: ###-#### Internet Inspection Request from: Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 1/28/2009 | 1/29/2009 | 1/29/2009 | A | PART |
Forrest France
|
|
|
Thrust blocking at two 45 deg. ells at the SE corner of the building are approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/27/2009 | 1/28/2009 | 1/28/2009 | A | PART |
Forrest France
|
|
|
See stamped plan set for UG pipe runs okay to bury.
|
INSP-Sprinkler Rough-in | 1/27/2009 | 1/27/2009 | 1/27/2009 | P | PART |
Forrest France
|
|
|
UG fire supply pipe per red-line annotations with todays date on approved plan set okayed for bury, (NE corner).
|
INSP-Sprinkler Rough-in | 1/14/2009 | 1/15/2009 | 1/15/2009 | A | PART |
Forrest France
|
|
|
See annotations initialed with today's date for location of two stubs and riser pieces okayed for cover at the south/central side of the building.
|
INSP-Sprinkler Rough-in | 1/12/2009 | 1/12/2009 | 1/12/2009 | P | CANC |
Forrest France
|
|
|
brian Phone #: ###-#### Inspection cancelled from web by: Jeff Packham
|
(F) Reprint permit | | | 1/12/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/12/2009 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/9/2009 | | 1/9/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2009 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/9/2009 | | 1/9/2009 | | DONE |
Cathy Brown
|
|
|
|
Telephone call | | | 1/9/2009 | | DONE |
|
|
|
lft vm with jeff anderson ###-#### that permit is ready to be picked and no fee
|
Permit Ready to Issue | | | 1/9/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/8/2009 | | |
Sam Rogers
|
|
|
Plan mod rec'd- three copies of application and plans
|
Issue and Print Permit | | | 11/20/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/19/2008 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/19/2008 | | 11/19/2008 | | DONE |
|
|
|
|
Telephone call | | | 11/19/2008 | | DONE |
|
|
|
t/c w jeff anderson at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 11/19/2008 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/12/2008 | | 11/18/2008 | | PASS |
|
|
|
plans are approved
|
Application received | | | 11/12/2008 | | |
|
|
|
|
Pending Assignment by SAM | 11/12/2008 | | 11/12/2008 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (SAM) | 1/8/2009 | | | | |
Sam Rogers
|
|
|
|