Miscellaneous action | | | 7/17/2009 | | DONE |
|
|
|
Taken to records for scanning.
|
INSP-Final Inspection | 6/10/2009 | 6/11/2009 | 6/11/2009 | A | PASS |
Forrest France
|
|
|
Remainder of fire alarm devices per the scope of work passed testing, permit finaled.
|
INSP-Alarm Testing | 5/13/2009 | 5/14/2009 | 5/14/2009 | A | PASS |
Troy Cobbley
|
|
|
Four smoke detectors and one manual pull station were tested. They are located in phase 5, sub phase 4 and 5. See the city approved plans with todays date and my name written at each device. Items tested ok.
|
INSP-Alarm Testing | 2/26/2009 | 3/2/2009 | 3/2/2009 | A | PART |
Forrest France
|
|
|
See locations initialed on approved plan set with today's date for three in duct detectors, two area detectors and two notification devices tested, noted one HVAC grill to be relocated as discussed.
|
INSP-Alarm Testing | 1/7/2009 | 1/8/2009 | 1/8/2009 | A | PART |
Forrest France
|
|
|
See approved plan set for locations of devices inspected and passed today including dampers, strobes, smoke detectors-noted one SD at the corridor address #58 to be relocated due to proximity to an HVAC diffuser, existing MP #101 tested okay.
|
Issue and Print Permit | | | 12/9/2008 | | DONE |
|
|
|
|
Alarm Plan Check | | | 11/28/2008 | | PASS |
|
|
|
see review comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/28/2008 | | DONE |
|
|
|
|
Telephone call | | | 11/28/2008 | | DONE |
Cathy Brown
|
|
|
lft vm with larry geyer 376-13-- ext 30 that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 11/28/2008 | | 11/28/2008 | | DONE |
Cathy Brown
|
|
|
|
Permit Ready to Issue | | | 11/28/2008 | | DONE |
Cathy Brown
|
|
|
|
Application received | | | 11/17/2008 | | |
|
|
|
|
Plan assigned to (Stephanie) | 11/17/2008 | | 11/17/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Case Summary | | | 11/17/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|