Miscellaneous action | | | 7/17/2009 | | DONE |
|
|
|
Taken to records for scanning.
|
INSP-Final Inspection | 6/22/2009 | 6/22/2009 | 6/22/2009 | A | PASS |
Forrest France
|
|
|
Record drawings accepted, fire alarm permit okayed for final status.
|
INSP-Final Inspection | 6/15/2009 | 6/15/2009 | 6/15/2009 | A | DONE |
Forrest France
|
|
|
Contact Mark Phone#: ###-####
|
INSP-Alarm Testing | 6/1/2009 | 6/1/2009 | 6/2/2009 | A | PART |
Forrest France
|
|
|
See stamped plan set for areas inspected to date.
|
INSP-Alarm Testing | 5/26/2009 | 5/29/2009 | 5/29/2009 | A | PART |
Forrest France
|
|
|
Completed fire alarm testing for the second floor classroom wings areas F and G. Noted three smoke detectors to be moved due to overspacing, one notification appliance is overspaced, also annotated field changes including deleted dampers, door holds and smoke detectors at some areas.
|
INSP-Alarm Testing | 5/26/2009 | 5/28/2009 | 5/28/2009 | A | PART |
Forrest France
|
|
|
Fire alarm testing completed for the second floor media center areas and adjacent corridors areas F and G, need access to test devices in one locked storage room, one SD to be added at the circulation desk, noted deleted points including door holders, dampers, relocated nac panel and deleted sd to be included on as-built set. Non-functional damper at the electrical room 1st floor retested okay after repair.
|
INSP-Alarm Testing | 5/26/2009 | 5/27/2009 | 5/27/2009 | A | PART |
Forrest France
|
|
|
Completed fire alarm testing for areas D and E first floor including the elevator-see plans for annotations. Noted one fire damper at the electrical room adjacent to the riser room which did not operate, retest for items noted yesterday okayed, as-builts for deleted points to be reflected on record drawings.
|
INSP-Alarm Testing | 5/25/2009 | 5/26/2009 | 5/26/2009 | A | PART |
Forrest France
|
|
|
Completed fire alarm testing for areas A, B, and C today. Noted on plans one smoke detector to be relocated, need to repair non-functional dampers at the cafeteria, deleted devices at the electrial room, kitchen and dampers at various locations must be indicated on record drawings. See plans for annotations.
|
INSP-Alarm Testing | 5/20/2009 | 5/20/2009 | 5/20/2009 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled due to being overbooked.
|
INSP-Alarm Testing | 5/18/2009 | 5/19/2009 | 5/19/2009 | P | CANC |
Troy Cobbley
|
|
|
Cancelled per conversation with Mark.
|
INSP-Conference | 5/18/2009 | 5/18/2009 | 5/18/2009 | P | DONE |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 5/18/2009 at 9:12:04 AM. Contact: ###-####.
|
INSP-Alarm Testing | 5/13/2009 | 5/14/2009 | 5/15/2009 | A | PART |
Forrest France
|
|
|
See permit activity comments for work completed to date.
|
INSP-Alarm Testing | 5/13/2009 | 5/15/2009 | 5/15/2009 | A | PART |
Forrest France
|
|
|
Testing completed for fire alarm notificaiton, initiation, and duct smoke detection for area "A" as marked on plan set. Still need record of inspection and testing forms and original stamped plan set, need to verify dB readings do not exceed max. allowed at the locker room and mechanical room entrys, provide correct descriptors matching sprinkler riser zones, verified account is set up, noted phone line troubles are not annunciated at the FACP-only indicated at the security panel.
|
INSP-Alarm Testing | 5/12/2009 | 5/13/2009 | 5/13/2009 | A | FAIL |
Troy Cobbley
|
|
|
The original city approved plans were not provided. All of the signals sent to the monitoring company were undefined even though I had been told that the monitoring had been set up. The phone line #2 did not report a trouble signal when disconnected. Labels need to be provided at the NAC panels and the fire sprinkler risers. See the onsite plans for devices tested on the first floor administrative area. These will need to be retested due to the signals not being sent. Also see this set of plans for room descriptions that smoke detectors had that did not match those on the plans. The NAC panels interconnection with the facp was verified for supervision. Both phone lines have separate phone numbers as well.
|
INSP-Alarm Testing | 5/7/2009 | 5/8/2009 | 5/8/2009 | A | NR |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 5/7/2009 at 4:35:36 PM. Contact: ###-####. Discussed items for final and project schedule.
|
FIR-Aging Inspection | 3/9/2009 | 3/9/2009 | 3/9/2009 | | DONE |
Forrest France
|
|
|
Site visit confirmed construction underway, work in progress.
|
Inspection Record Card- Fire | 12/8/2008 | | 12/8/2008 | | DONE |
|
|
|
|
Telephone call | | | 12/8/2008 | | DONE |
|
|
|
left message w laura for charlie bayne at ###-#### - permit ready - no fees due
|
Permit Ready to Issue | | | 12/8/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/8/2008 | | DONE |
|
|
|
|
Alarm Plan Check | | | 12/5/2008 | | PASS |
|
|
|
See redlines and review comments. NOTE: plans will need to be resubmitted with changes implemented prior to scheduling for an inspection.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2008 | | DONE |
|
|
|
|
Telephone call | | | 12/2/2008 | | DONE |
|
|
|
Spoke to Charlie and requested a data sheet for the lexan horn/strobe guards
|
Application received | | | 11/20/2008 | | |
|
|
|
|
Plan assigned to (Stephanie) | 11/20/2008 | | 11/20/2008 | | DONE |
Stephanie L. Cobbley
|
|
|
|