INSP-Final Inspection | 7/28/2009 | 7/29/2009 | 7/30/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2009 | 5/12/2009 | 5/12/2009 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test including the fdc passed
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2009 | 5/6/2009 | 5/6/2009 | A | PART |
Troy Cobbley
|
|
|
Both of the above ground hydro tests failed. The wet system had visable leakage on the mezzanine. The FDC was not part of the hydro test and wil need to be included as per NFPA 13. The corrections noted on the previous inspection have been corrected and the remaining piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2009 | 5/5/2009 | 5/5/2009 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints.
|
(F) Reprint permit | | | 5/5/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/5/2009 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 4/27/2009 | | 5/4/2009 | | DONE |
Tim Frost
|
|
|
5/4/2009 13:50:55 TRF - activity updated through activity FIRA22 from case FIR08-00855.
|
Sprinkler Plan Check | 5/4/2009 | | 5/4/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/2009 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 5/4/2009 | | DONE |
|
|
|
t/c bryan johnson at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/4/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/27/2009 | | |
Barbara Stitt
|
|
|
|
Case Summary | | | 4/22/2009 | | |
|
|
|
|
INSP-Sprinkler Rough-in | 4/17/2009 | 4/20/2009 | 4/20/2009 | P | PART |
Troy Cobbley
|
|
|
Seven upright heads need to be added as marked on the city approved plans. One piece of sprinkler piping on the plans has no designation and 4" piping has been installed where 3" is shown on the plans. Sprinkler piping can be covered except where these problems are located.
|
Permit Ready to Issue | | | 4/17/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Telephone call | | | 4/17/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
Rob no longer works there- told receptionist permit was ready
|
(F) Reprint permit | | | 4/17/2009 | | DONE |
Tisha Gallop
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/17/2009 | | DONE |
Tisha Gallop
|
|
|
|
Sprinkler Plan Check | 4/16/2009 | | 4/16/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2009 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 4/10/2009 | | |
Tim Frost
|
|
|
|
Case Summary | | | 4/10/2009 | | |
|
|
|
|
Sprinkler Plan Check | 4/1/2009 | | 4/1/2009 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Telephone call | | | 4/1/2009 | | DONE |
|
|
|
left vm for bryan johnson at ###-#### - permit denied - needs to be picked up and resubmitted
|
Plan assigned to (Tim) | 3/19/2009 | | 4/1/2009 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 3/19/2009 | | |
Tisha Gallop
|
|
|
Received three copies of submittal booklet and plan sheets FP1, FP2, FP3; taken to Fire Review
|
Plan resubmittals received | | | 3/19/2009 | | |
Tim Frost
|
|
|
|
INSP-Sprinkler Rough-in | 2/27/2009 | 2/27/2009 | 3/2/2009 | P | PASS |
Troy Cobbley
|
|
|
Ok to Cover Foyers on the first floor but not outside the foyers which are protected from the above systems. Ok to Cover Rooms 150 and 151, and bathrooms on First Floor.
|
INSP-Sprinkler Rough-in | 2/26/2009 | 2/26/2009 | 2/26/2009 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled per the fire sprinkler contractor.
|
INSP-Sprinkler Rough-in | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | FAIL |
Troy Cobbley
|
|
|
Resubmittal of drawings required. Drawings do not match installation. Antifreeze system was installed instead of the dry system that was shown on the plans.
|
Inspection Record Card- Fire | 1/8/2009 | | 1/8/2009 | | DONE |
|
|
|
|
Telephone call | | | 1/8/2009 | | DONE |
|
|
|
t/c w lillie at shilo ###-#### - permit ready
|
Permit Ready to Issue | | | 1/8/2009 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/8/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan resubmittals received | | | 1/7/2009 | | DONE |
|
|
|
Received 3 re-submittal fire plans sent to fire ///DLD
|
Sprinkler Plan Check | 1/7/2009 | | 1/7/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2009 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/31/2008 | | 12/31/2008 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments
|
Telephone call | | | 12/31/2008 | | DONE |
|
|
|
t/c w rob colman at ###-#### - permit denied - needs to be picked up for resubmittal
|
Application received | | | 12/23/2008 | | |
|
|
|
|
Pending Assignment by SAM | 12/23/2008 | | 12/23/2008 | | DONE |
Tim Frost
|
|
|
|