INSP-Final Inspection | 4/2/2009 | 4/3/2009 | 4/3/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The forward flow test and alarm system interconnection passed.
|
Telephone call | | | 2/10/2009 | | DONE |
|
|
|
Spoke with Tony Larson at Viking. He said the project was done except that he was waiting for the alarm tie in. (dedicated phone line) After the alarm tie in he could final.
|
Inspection Record Card- Fire | 1/9/2009 | | 1/9/2009 | | DONE |
Cathy Brown
|
|
|
|
Permit Ready to Issue | | | 1/9/2009 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/9/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Sprinkler Plan Check | 1/8/2009 | | 1/8/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There ARE annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/8/2009 | | DONE |
|
|
|
|
Telephone call | | | 1/8/2009 | | DONE |
|
|
|
Spoke with Tony Larson regarding heads around the new walls. He indicated to me with dimensions that the new walls that go to the deck do not pose a problem to the existing fire protection. The space still has adequate fire protection without any over spaced sprinklers. He was not sure if the back door area had fire protection. He said if it did not have adequate fire protection that it would be added. I indicated that I would mark the plans to verify in the field which I did.
|
Application received | | | 1/6/2009 | | |
|
|
|
|