Permit NumberFIR09-00027
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 234 S WHISPERWOOD
Project NameMEP GROUP LLC
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of 165'x6" underground ONLY. The above system will follow at a later date under a separate permit.

The MEP Group Office Shell - To construct a new 11,580 square foot, one story with a 1,445 square foot mezzanine, wood framed office shell building and related site improvements. This building is designed for two future office tenant spaces. This is a shell permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. This building will be fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Sprinkler Rough-in/Hydro5/19/20095/20/20095/20/2009APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection5/19/20095/20/20095/20/2009APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection5/14/20095/15/20095/15/2009APART
DetailsForrest France
UG fire supply line flush completed satisfactory.
INSP-Sprinkler Rough-in/Hydro4/14/20094/15/20094/15/2009APASS
DetailsTroy Cobbley
The underground hydro test passed
INSP-Sprinkler Rough-in3/23/20093/23/20093/23/2009PPASS
DetailsTroy Cobbley
The thrust block at the 45 has been replaced and the remaining underground piping can be covered.
INSP-Sprinkler Rough-in3/18/20093/19/20093/23/2009PPASS
DetailsTroy Cobbley
The thrust block at the 45 has been replaced and the remaining underground piping can be covered.
INSP-Sprinkler Rough-in/Hydro3/19/20093/20/20093/20/2009AFAIL
DetailsForrest France
Thrust block at the 45 deg ell is not satisfactory, noted one section of piping needs properly bedded, remiander of installation is okay for cover-see plans for locations approved for bury.
INSP-Final Inspection2/26/20092/27/20092/26/2009PCANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 2/26/2009 at 2:54:20 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Feb 26 2009 2:56PM.
INSP-Sprinkler Rough-in1/23/20091/23/20091/23/2009PPASS
DetailsTroy Cobbley
The in building riser and 5'-0" stub out are ok to bury
Inspection Record Card- Fire1/21/2009 1/21/2009 DONE
DetailsCathy Brown
Telephone call  1/21/2009  
DetailsCathy Brown
tlk to jeff anderson ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  1/21/2009 DONE
DetailsCathy Brown
Issue and Print Permit  1/21/2009 DONE
DetailsAlexandra L. DeYoung
Plan resubmittals received  1/20/2009  
DetailsSam Rogers
Plan mod rec'd- copy of app and three copies of plans- taken to fire review
Sprinkler Plan Check1/20/2009 1/20/2009 DONE
DetailsTim Frost
See attached comments
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  1/20/2009 DONE
Application received  1/16/2009 FAIL
Application denied. Scope of work exceeds the limited criteria for a quick permit. 1/20/09. Faxed and emailed infromation to applicant.
Pending Assignment by SAM1/16/2009 1/16/2009 DONE
DetailsTim Frost