Permit Information
Permit NumberFIR09-00033
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2390 E FREIGHT ST
Project NameWinco Distribution Center
Customer Number 
ePlanReview 
Description
See comments for sprinkler count
The Fire Sprinkler Scope of work consists of thirty-two sprinkler system(s) to protect a warehouse and three ancillary buildings. The commodities include, class II, class IIIB, class IV and wood pallet. There are also office and maintenance areas. The system utilizes ESFR, Extra Large Orifice and Standard Sprinklers. There is a diesel driven fire pump rated at 3000 GPM @ 125 PSI in a separate building. There are twelve lead ins.


Partial Review ONLY

This is a partial review of the wet systems only. The dry systems and ancillary buildings will follow at a later date. The fire pump equipment has been reviewed but NOT the fire pump building since the plans are incomplete. System 9 has not been reviewed since the rack drawings have not been provided.


Building Scope

Winco Foods Distribution Center (Shell Only) - To construct a new 712,555 square foot, one story, concrete tilt-up and steel frame warehouse shell building and related site improvements. This building will contain dry goods, cooler and freezer warehouse areas, as well as, office and maintenance support areas. This building is fully fire sprinkled. The sprinklers are used for area. This building is an unlimited area building. Minimum 60 foot open yards and public ways must be maintained around this building. This permit is for a cold shell only and no occupancy is allowed under this permit. A separate tenant improvement permit is required to finish this building for occupancy. Separare permits are required to construct the other proposed accessory buildings. All construction per the approved plans and attached comment list. DRH07-00594 JCM

Systems Design Information and Criteria
Water supply information provided by United Water is: 90 psi static, 20 psi residual 4000 gpm dated,
01-30-09, 2390 Freight Street.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan resubmittals received  6/17/2014 DONE
DetailsTim Frost
INSP-Final Inspection11/10/200911/12/200911/12/2009APASS
DetailsForrest France
Correction items verified for completion, final walkthrough passed, fire sprinkler permit finaled.
INSP-Final Inspection9/15/20099/16/20099/17/2009APART
DetailsForrest France
TOC approved
INSP-Alarm Testing8/27/20098/27/20098/28/2009PPART
DetailsForrest France
Continued inspection completed 8/27 afternoon and evening by F. France and B. Johnson for the remainder project related fire alarm permit work FIR09-00296 including correction items. Room signage, building map, program changes, and breaker lock okayed, vesda faults tested okay, signals at main FACP verified, low air supervisory signals tested, alert and alarm signals sent/recieved, transport times at several systems measured and found to be under max. time limits, systems 22, 23, 24, 25 and 17 passed, system 18 failed. Continued testing while system 18 repaired. Sequence of operation passed for the freezer systems including rack systems 26,27,28,29, and area served. Repairs at system 18 modules and VESDA completed and retested okay per B. Johnson. Final pending NFPA 72 record of inspection and testing and record of completion documents for signature.
INSP-Alarm Testing8/25/20098/26/20098/28/2009PFAIL
DetailsForrest France
Duplicate inspection for am/pm time frames...Comments are as follows- Items noted during a lengthy inspection completed 8/26 morning and afternoon include failure to initiate alarm condition at the first three single interlock systems checked 16, 19, and 20, missing labels at some VESDA units, led lamps do not illuminate at some modules on trouble condition at the freezer vesdas, noted end cap locations at the floor level have not been installed per design-caps are now at the ceiling deck at all systems. After program changes made while on site, alarm condition for the single interlock system 16 rechecked and found to incorrectly initiate solenoid release for all fourteen single and double interlock systems, overspacing of detectors at systems 16,17,18 and 21 okayed after repairs made, continued testing after more program changes showed systems 19, 20, 21, and 16 functioned correctly.
INSP-Alarm Testing8/25/20098/26/20098/28/2009AFAIL
DetailsForrest France
Items noted during a lengthy inspection completed 8/26 morning and afternoon include failure to initiate alarm condition at the first three single interlock systems checked 16, 19, and 20, missing labels at some VESDA units, led lamps do not illuminate at some modules on trouble condition at the freezer vesdas, noted end cap locations at the floor level have not been installed per design-caps are now at the ceiling deck at all systems. After program changes made while on site, alarm condition for the single interlock system 16 rechecked and found to incorrectly initiate solenoid release for all fourteen single and double interlock systems, overspacing of detectors at systems 16,17,18 and 21 okayed after repairs made, continued testing after more program changes showed systems 19, 20, 21, and 16 only functioned correctly.
INSP-Sprinkler Rough-in/Hydro8/25/20098/25/20098/28/2009PDONE
DetailsForrest France
Duplicate inspection request-see activity notes for details.
INSP-Sprinkler Rough-in8/21/20098/25/20098/28/2009AFAIL
DetailsForrest France
See C/N on site for inspection comments completed 8/26 by T. Frost--System 13 had an HVAC duct blocking the sprinklers at column line C.
System 11 needs sprinklers in the doorway areas.
System 14 Ceiling tile missing through out. In the scan department of system 14 there cannot be storage on the top level of the racks.
City of Boise still has not received a letter from Peerless Pump on the malfunctioning PLD.
System 21 condensate piping is blocking a sprinkler head.
All dry storage systems. The 4x4 structural tubing has not been removed and the ESFR sprinklers are blocked.
INSP-Sprinkler Rough-in/Hydro8/25/20098/26/20098/28/2009APART
DetailsForrest France
See inspection comments per T. Frost completed 8/26-System 30 Sprinklers are required below the tanks since they are greater than 4' wide.
One small room had two drops but no pendent sprinklers or ceiling. A ceiling will need to be installed along with the pendent sprinklers or the heads cut back and upright sprinklers installed. Hydro passed.
INSP-Alarm Testing8/21/20098/25/20098/25/2009PFAIL
DetailsForrest France
Alarm Testing for preaction activation. Phone #: ###-#### Internet Inspection Request from: Jeff Packham ATTN: See notes for FIR09-00296--Deficient items found during the first three hours of inspection include missing NFPA 72 Record of Inspection and Testing with a copy of supervising station signals report per plan review note #3, missing signage per review note #1, provide a lock and label at the power circut breaker to the panel, A/C power off failed to report to the main FACP-see note #5, per details on approved plans 90 deg. ells to be avoided and 6" to 10" clearance to be provided at each side of the freezer wall to avoid ice plugs-noted significant frosting at these locations, the first VESDA fault at system 28 did not report, plans incorrectly show location of system 27, south line of smoke detection at systems 16,17, and 18 are overspaced-see fire code review note #13, provide a building map at the releasing panel indicating floorplan layout and locations of all initiating devices-see plan review note #15, repairs underway at VESDA system 29.
INSP-Sprinkler Rough-in8/21/20098/24/20098/24/2009PPART
DetailsForrest France
Completed rough-in inspections for systems 23 and 24 including coverage at six rooftop towers, pallet storage single interlock systems 16,17, and 18, reinspection for correction items at system 25, discussed remaining issues at systems 14, 18 and 21 including pipe size changes, racks at the scan room, obstruction at HVAC piping, coverage at ceiling elevation change between system 14 and 11, and inspection schedule for project related FIR 09-00296 fire alarm permit for VESDA and preaction system releasing panel site acceptance testing set for the first requested inspection 8/25.
INSP-Sprinkler Rough-in/Hydro8/24/20098/24/20098/24/2009APART
DetailsForrest France
Hydrostatic retest of rack system #6 at the dry goods warehouse passed.
INSP-Alarm Testing8/21/20098/25/20098/24/2009ANR
DetailsForrest France
Pending FIR09-00296
INSP-Alarm Testing8/21/20098/24/20098/24/2009PNR
DetailsForrest France
Pending FIR09-00296
INSP-Alarm Testing8/21/20098/24/20098/24/2009ANR
DetailsForrest France
Pending FIR09-00296
INSP-Sprinkler Rough-in/Hydro8/21/20098/21/20098/21/2009PFAIL
DetailsForrest France
Overhead hydrostatic test for the class IIIB liquid rack system failed due to visible leakage at two locations.
INSP-Alarm Testing8/21/20098/21/20098/21/2009PPART
DetailsForrest France
Retest for failed pressure switch at rack system #27 passed, per contractor pretesting for double and single interlock preaction valve solenoid operations has been completed.
INSP-Sprinkler Rough-in8/14/20098/21/20098/21/2009APART
DetailsForrest France
C/N items at the dry goods warehouse rack system verified for completion, final walkthrough at the dry goods office area okayed-one escutcheon installed while on site, corrections for obstructions at HVAC units in the dry goods warehouse are finished, fire sprinkler work below overhead pallet storage at the perishables docks is underway.
INSP-Sprinkler Rough-in8/14/20098/20/20098/21/2009PPART
DetailsForrest France
Walkthrough completed for systems 14 and 31-see inspection notes for FIR09-00363, also finished sprinkler monitoring tests with the exception of preaction system low air signals/ solenoid operation. Pressure switch at system 27 needs replaced, noted new sprinkler line below overhead pallet storage east dock area, corrections at the dry goods warehouse not yet completed.
INSP-Alarm Testing8/20/20098/20/20098/21/2009PPART
DetailsForrest France
The remainder of riser supervision at systems in rooms #4 and #5 tested with the exception of low air signals monitored by a separate panel not ready for testing. Pressure switch at system 27 is still not functional and failed to initiate an alarm condition upon waterflow.
INSP-Alarm Testing8/19/20098/19/20098/20/2009PPART
DetailsForrest France
Inspection for riser supervision completed at the remainder of systems on the south side of the building through riser room #4 with the exception of solenoid operation at the interlock/vesda and low air supervisory signals at riser 2 and 4, pre-testing/adjustments done while on site, panel trouble conditions also cleared while waiting on site, one flow switch at freezer system 27 failed to operate. Will test the remainder of sprinkler system monitoring as discussed.
INSP-Sprinkler Rough-in8/14/20098/19/20098/20/2009AFAIL
DetailsForrest France
Inspection for the class IIIB liquid storage racks system failed due to field installation discrepancies with the approved design layout including head spacing and gridded piping at some locations, also noted missing solid shelving between levels above the forklift aisles. Note: Hydrostatic testing completed- however will need to be redone due to pending modifications for this system.
INSP-Sprinkler Rough-in8/14/20098/18/20098/18/2009APASS
DetailsTroy Cobbley
Rough-in passed for systems 21 and 22. One upright head on system 21 is blocked by a 2 x4 and is noted on the plans. I also spoke to Jeff Packham about the additional 90 elbows that have been added in the remote area of system 22. He is going to verify that it does not adversly effect the system hydraulic calculations.
INSP-Sprinkler Rough-in8/14/20098/17/20098/18/2009APART
DetailsForrest France
See comments per site visit completed by T. Cobbley.
INSP-Sprinkler Rough-in/Hydro8/17/20098/17/20098/17/2009PFAIL
DetailsTroy Cobbley
No approved fire sprinkler plans were on site so no inspection was performed.
INSP-Sprinkler Rough-in8/14/20098/14/20098/14/2009PCANC
DetailsForrest France
Overbooked
INSP-Sprinkler Rough-in/Hydro8/12/20098/12/20098/12/2009PPASS
DetailsTroy Cobbley
Systems 19 and 20 were inspected today. The rough-in inspection generally passed but obstructions to the upright sprinkler heads and incorrect hanger ring sizing has been marked in red on the city approved plans.
INSP-Sprinkler Rough-in/Hydro8/4/20098/11/20098/12/2009PNR
DetailsForrest France
Rack system at the dry goods area is not yet complete, corrections for obstructions at beams and HVAC units are underway at noted locations for ESFR heads, need to test alarm interconnections at remaining riser systems 11 and up.
INSP-Sprinkler Rough-in/Hydro8/4/20098/11/20098/11/2009APASS
DetailsTroy Cobbley
Rough-in inspections for sprinkler systems 16, 17, 18 and 25 are passed. There are some the the typical 4x4 beam obstructions on system 25 that will need addressed. Also we started the rough-in inspection on system 24 but found beams blocking the upright sprinkler heads in the areas under the roof penthouses. I spoke to Jeff Packham on the phone about these obstructions and he stated he would be out in the afternoon to investigate.
INSP-Sprinkler Rough-in/Hydro8/4/20098/10/20098/10/2009PDEFR
DetailsForrest France
INSP-Sprinkler Rough-in/Hydro8/4/20098/10/20098/10/2009ADEFR
DetailsForrest France
INSP-Sprinkler Rough-in/Hydro8/4/20098/6/20098/6/2009PPART
DetailsForrest France
Overhead rough-in inspection for system #15 passed-see dated initials on plans.
INSP-Sprinkler Rough-in/Hydro8/4/20098/6/20098/6/2009APART
DetailsForrest France
Concluded satisfactory 24 hr. pneumatic retest of the overhead preaction systems #26,27,28 and 29.
INSP-Sprinkler Rough-in/Hydro8/4/20098/7/20098/6/2009PDEFR
DetailsForrest France
Duplicate inspection
INSP-Sprinkler Rough-in/Hydro8/4/20098/7/20098/6/2009ADEFR
DetailsForrest France
INSP-Sprinkler Rough-in/Hydro8/4/20098/5/20098/5/2009PPART
DetailsForrest France
OH rough-in for systems 11 and 13 completed today-see plans for changes to be made at the electrical room system 13.
INSP-Sprinkler Rough-in/Hydro7/29/20098/5/20098/5/2009APART
DetailsForrest France
Overhead hydrostatic testing for systems 31, 23,24,17 not including 4" rack system, 25,riser room#3, riser room#4, and 18 not including the 4" rack system passed.
INSP-Sprinkler Rough-in/Hydro7/29/20098/4/20098/4/2009APART
DetailsForrest France
Begin hydrostatic testing for system #18, riser #4, and all systems in riser room #3.
INSP-Sprinkler Rough-in/Hydro7/29/20098/3/20098/3/2009APART
DetailsForrest France
Hydrostatic testing for systems 14, 21, 22, and riser room system #2 completed satisfactory. Overhead rough-in for the remainder of system 14 passed, -noted three locations where comm wire attatchments to the sprinkler piping need to be removed, system 31 OH rough-in okayed except at one storage room where walls need to extend to the deck for area separation.
INSP-Sprinkler Rough-in7/31/20097/31/20097/31/2009APART
DetailsForrest France
System 14 rough-in and cover inspection completed for drop ceilings at areas as marked on stamped plan set. Noted minor modifications to floorplan and head layout okayed. One red-lined group of rooms already covered will need to be exposed for inspection as discussed.
INSP-Sprinkler Rough-in/Hydro7/24/20097/31/20097/31/2009APART
DetailsForrest France
Completed satisfactory fire alarm testing for riser supervision at the dry goods warehouse area with the exception of the dry goods rack system currently under construction. PIV's, system control valves, flow switches tested okay, one flow switch at system #6 adjusted while on site, missing test orfice for the ESFR overhead systems also installed.
INSP-Sprinkler Rough-in/Hydro7/24/20097/30/20097/30/2009AFAIL
DetailsForrest France
24 hr. air testing concluded at 4:00 for the preaction systems at the freezer. Overhead systems #27 lost 13psi, #26 lost 4psi, #28 lost 3psi, #29 lost 9psi. NOTE: The rack systems #27, 26, 28, and 29 passed pneumatic test with no pressure loss at the guage.
INSP-Sprinkler Rough-in/Hydro7/24/20097/29/20097/29/2009APART
DetailsForrest France
Begin 24 hr. pneumatic testing for 8 preaction systems at the freezer area including rack and overhead systems-start time @ 4:00pm.
INSP-Sprinkler Rough-in/Hydro7/21/20097/28/20097/29/2009APART
DetailsForrest France
Continuing rough in inspections and hydro tests. Please call with time frames. Phone #: ###-#### Internet Inspection Request from: Jeff Packham
INSP-Sprinkler Rough-in/Hydro7/21/20097/27/20097/27/2009APART
DetailsForrest France
Overhead hydrostatic testing completed okay for systems 13, 15, riser room #1, 19, 20 and system 16 not including racks.
INSP-Sprinkler Rough-in/Hydro7/24/20097/24/20097/24/2009PPART
DetailsForrest France
Trip testing completed acceptable for rack systems # 26 and 27 at the freezer area.
INSP-Sprinkler Rough-in/Hydro7/21/20097/24/20097/24/2009APART
DetailsForrest France
Hydrostatic re-test for systems #1, 2 and 5 passed.
INSP-Sprinkler Rough-in/Hydro7/23/20097/23/20097/23/2009PPART
DetailsForrest France
Trip testing for rack systems #28 and 29 completed satisfactory.
INSP-Sprinkler Rough-in/Hydro7/16/20097/23/20097/23/2009APART
DetailsForrest France
Overhead hydrostatic testing for rack systems #26 and 27 completed acceptable.
INSP-Sprinkler Rough-in/Hydro7/22/20097/22/20097/22/2009PPART
DetailsForrest France
OH hydrostatic testing for systems #28, 28 rack, 29, 29 rack, 27, 28 and riser room 5 passed.
INSP-Sprinkler Rough-in/Hydro7/16/20097/22/20097/22/2009APART
DetailsForrest France
Rough-in inspection completed for OH system #26, noted items include beam obstructions as previously noted, one sprig-up spaced incorrectly, main change at a different location than what is shown on stamped plans, EQ bracing shown but not installed.
INSP-Sprinkler Rough-in/Hydro7/21/20097/21/20097/21/2009PNR
DetailsForrest France
Rack system trip tests and overhead hydrostatic tests not ready. Rough-in inspection completed for system #27.
INSP-Sprinkler Rough-in/Hydro7/16/20097/21/20097/21/2009APART
DetailsForrest France
Continuiong rough in inspections and hydro tests. Please call with time frame. Phone #: ###-#### Internet Inspection Request from: Jeff Packham
INSP-Sprinkler Rough-in/Hydro7/20/20097/20/20097/20/2009PPART
DetailsForrest France
Completed timed and functional trip testing for overhead double interlock systems # 26, 27, 28, and 29 at the freezer not including the rack systems or fire alarm interconnections.
INSP-Sprinkler Rough-in/Hydro7/16/20097/20/20097/20/2009ADONE
DetailsForrest France
Duplicate inspection request
INSP-Sprinkler Rough-in/Hydro7/10/20097/17/20097/17/2009ACANC
DetailsTroy Cobbley
Cancelled due to time constraints.
INSP-Sprinkler Rough-in/Hydro7/10/20097/16/20097/16/2009APASS
DetailsTroy Cobbley
The remainder of system #6 and all of system #9 passed rough-in inspection except for the re-occuring issues with the 4x4 structural beam and the duct/roof penatrations. The racking piping below system #9 was not included in this inspection.
INSP-Sprinkler Rough-in7/8/20097/15/20097/16/2009PPART
DetailsTroy Cobbley
Fire pump curve certification passed pending acceptance of the non-functioning PLD due to possible water surge. Lucas with Peerless Pump stated that this is not a problem during a fire condition. The pump provided 472 gpm at 150% which is more than required.
INSP-Sprinkler Rough-in7/8/20097/15/20097/16/2009AFAIL
DetailsTroy Cobbley
Time tests for double interlock preaction systems at freezers unable to be completed due valves could not be set up.
INSP-Sprinkler Rough-in/Hydro7/10/20097/14/20097/15/2009APASS
DetailsTroy Cobbley
Rough-in complete on systems #7 and #8. Tim Frost verified that the 4x4 structural members will be considered obstructions and will need to be addressed on all systems. Also the ducting/roof penatrations will require sprinkler protection below them. This was addressed with Jeff with treasure valley fire.
INSP-Sprinkler Rough-in/Hydro7/10/20097/13/20097/13/2009APART
DetailsTroy Cobbley
Rough in for all of system #4, #5 and the south portioin of #6 passed. I did note 4x4 structural beams place directly below ESFR heads in many locations that may cause an obstruction to the sprinkler coverage. Also one duct/roof penatration in the middle of system #5 appears to have the half spacing of the ESFR pendants exceeded. A data sheet for the ESFR heads was not available on the job site for listing/design reference for the heads. Per Russ it will be available tomorrow. He is also following up with Jeff in the office on the items listed above. No hydro testing was performed today.
INSP-Sprinkler Rough-in/Hydro7/10/20097/10/20097/10/2009PPART
DetailsForrest France
Overhead hydrostatic tests for systems #3 thru 11 at the dry goods warehouse passed with the exception of system #5 where visible leakage at one coupling was noted. Hydrostatic test for system #12 office area also completed acceptable.
INSP-Sprinkler Rough-in/Hydro7/10/20097/10/20097/10/2009AFAIL
DetailsForrest France
Hydrostatic test for systems #1 and #2 failed due to pressure loss at the guage and visible leakage at some locations.
INSP-Sprinkler Rough-in7/8/20097/9/20097/10/2009APART
DetailsForrest France
Rough-in inspections for systems #2 and #3 completed acceptable.
INSP-Sprinkler Rough-in7/7/20097/8/20097/8/2009APART
DetailsForrest France
Partial inspection for system #2 completed, noted one leaking coupling, discussed possible obstructions at HVAC units, hangers and pipe sizing appear okay, spacing and head locations at some areas need to be verified at the deck, discussed inspectors test connection orfice sizing at riser manifolds.
INSP-Sprinkler Rough-in/Hydro7/6/20097/7/20097/7/2009APASS
DetailsTroy Cobbley
System #1 rough-in inspection passed. Due to time constraints no other systems were inspected.
INSP-Sprinkler Rough-in/Hydro6/23/20096/24/20096/24/2009APART
DetailsForrest France
Partial pump acceptance testing completed today including the controler and driver units. Flow test not performed due to excessive inlet pressure.
Plan assigned to (Tim)6/23/2009 6/23/2009 DONE
DetailsTim Frost
6/23/2009 14:17:34 TRF - activity updated through activity FIRA22 from case FIR09-00033.
Sprinkler Plan Check6/23/2009 6/23/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  6/23/2009 DONE
DetailsTim Frost
Inspection Record Card- Fire6/23/2009 6/23/2009 DONE
Details
Telephone call  6/23/2009 DONE
Details
left vm for jeff packham at ###-#### - permit ready and fees given
Permit Ready to Issue  6/23/2009 DONE
Details
Issue and Print Permit  6/23/2009 DONE
Meeting  6/8/2009 DONE
DetailsTim Frost
Discussed 13' versus 12" between levels of in rack sprinklers in the class IIIB liquid racks. There were representatives from Treasure Valley Fire Protection, Epstein, City of Boise, Winco (via Phone), FM (via Phone) present at the meeting. The discussion focused on NFPA and FM standards states that 12' is maximum allowed between levels of in rack protection. FM indicated they think 13' is acceptable. FM was unable to supply engineering equivalency that 13' was acceptable. Mark Senteno Fire Marshall agreed to allow the 13'. He seemed to believe that FM was in the position to be able to make an informed decision.
Plan assigned to (Tim)5/5/2009 6/8/2009 DONE
DetailsTim Frost
6/8/2009 11:18:34 TRF - activity updated through activity FIRA22 from case FIR09-00363.
Plan assigned to (Tim)5/5/2009 5/19/2009 DONE
DetailsTim Frost
05-12-09 Resubmittal On Hold Winco\waiting on more info.
Sprinkler Plan Check5/19/2009 5/19/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Meeting  5/19/2009 DONE
DetailsTim Frost
Out take meeting with Jeff Packham. Discussed missing information required to complete the plan review. Some of the major items were as follows:
Correlate rack type in the elevations views with the plan views.
Show which criteria he is following for each rack type from either NFPA 13 or 30.
Staggered spacing
Show barriers
Telephone call  5/7/2009 DONE
Jeff told me to hold on to Winco since it was only one permit and could not be issued until ALL of the systems were approved.
Plan resubmittals received  5/5/2009  
DetailsTim Frost
Rec'd 3 copies of app, 2 submittal binders, and 3 plans- taken to Tim Frost
Meeting  4/23/2009 DONE
DetailsTim Frost
After careful review of various codes, it has been concluded, since this project is in a area B seismic zone that seismic hangers are NOT required.
Plan assigned to (Tim)4/7/2009 4/13/2009 DONE
DetailsTim Frost
Sprinkler Plan Check4/13/2009 4/13/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Miscellaneous action  4/13/2009 DONE
Emailed review comments
Telephone call  4/13/2009 DONE
Details
left vm for jeff at ###-#### - permit rejected - needs to be picked up and resubmitted
Plan resubmittals received  4/7/2009  
DetailsTim Frost
Early Start  2/6/2009 DONE
Approved Early Start request. Doc Attached.
Sprinkler Plan Check2/3/2009 2/3/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Telephone call  2/3/2009 DONE
tlk to jeff packham ###-#### that permit has been rejected
Miscellaneous action  1/23/2009 DONE
Email of questions and answers. Please, see attached pdf
Application received  1/20/2009  
Pending Assignment by SAM1/20/2009 1/20/2009