Miscellaneous action | | | 10/26/2009 | | DONE |
|
|
|
Fire alarm plans taken to records
|
INSP-Final Inspection | 10/20/2009 | 10/20/2009 | 10/20/2009 | P | PASS |
Troy Cobbley
|
|
|
The syncing of the handicap rooms a/v's has been addressed. The placement and testing of the atrium smoke detectors has been addressed. Permit finaled.
|
Alarm Plan Check | 10/19/2009 | | 10/19/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modification approved with redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 10/19/2009 | | DONE |
|
|
|
Approved plan modification plans available at front counter
|
Inspection Record Card- Fire | 10/19/2009 | | 10/19/2009 | | DONE |
|
|
|
|
Telephone call | | | 10/19/2009 | | DONE |
|
|
|
t/c w bryan colson at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 10/19/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/19/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/19/2009 | | |
|
|
|
|
INSP-Alarm Testing | 4/9/2009 | 4/9/2009 | 4/9/2009 | P | PASS |
Troy Cobbley
|
|
|
This inspection was a fire alarm rough-in on the first and second floors which passed. The horns on all floors of this building have been relocated to meet the requirements of NFPA 72.
|
INSP-Alarm Testing | 4/3/2009 | 4/6/2009 | 4/6/2009 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was for the fire alarm rough-in for the 3rd floor of building "B". The rough-in in general passed except that the horns in the rooms are not mounted at the correct heights as per NFPA 72 - 7.4. Per a conversation with Mike the strobes will be relocated to meet code requirements. Also no fixtures have been installed which may cause obstruction problems.
|
INSP-Alarm Testing | 4/2/2009 | 4/3/2009 | 4/3/2009 | A | FAIL |
Troy Cobbley
|
|
|
Approved drawings could not be found when I arrived at the job site. Will be rescheduled for monday.
|
Issue and Print Permit | | | 3/9/2009 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Stephanie) | 2/26/2009 | | 3/5/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 3/5/2009 | | 3/5/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See redlined plans and review comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2009 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 3/5/2009 | | 3/5/2009 | | DONE |
|
|
|
|
Telephone call | | | 3/5/2009 | | DONE |
|
|
|
t/c w michael pemberton at ###-#### - permit ready and no fees due
|
Permit Ready to Issue | | | 3/5/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/26/2009 | | |
Stephanie L. Cobbley
|
|
|
received application, letter from Curry Architecture, product info, plan sheets A1.1, FA0, FA0.1, FA0.2, FA0.3, FA1.1, FA1.1.1, FA1.1.2, FA1.1.3, FA1.2, FA1.2.1, FA1.2.2, FA1.2.3, FA2.1, FA2.1.1, FA2.1.2, FA2.1.3, FA2.2, FA2.2.1, FA2.2.2, FA2.2.3, FA3.1, FA3.1.1, FA3.1.2, FA3.1.3, FA3.2, FA3.2.1, FA3.2.2, FA3.2.3, FA4, FA5, FA6.1, FA6.2, FA7; taken to Fire Review
|
Plan assigned to (Stephanie) | 1/28/2009 | | 2/11/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 2/11/2009 | | 2/11/2009 | | FAIL |
Stephanie L. Cobbley
|
|
|
see redlines and review comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2009 | | DONE |
|
|
|
denied plans available at front counter
|
Miscellaneous action | | | 2/11/2009 | | DONE |
|
|
|
faxed review comments to contractor
|
Application received | | | 1/28/2009 | | |
|
|
|
|