Miscellaneous action | | | 10/26/2009 | | DONE |
|
|
|
Fire alarm plans taken to records
|
INSP-Final Inspection | 10/20/2009 | 10/20/2009 | 10/20/2009 | P | PASS |
Troy Cobbley
|
|
|
The syncing of the handicap rooms a/v's has been addressed. The placement and testing of the atrium smoke detectors has been addressed. Permit finaled.
|
Plan assigned to (Stephanie) | 10/15/2009 | | 10/19/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
10/19/2009 15:46:28 SLC - activity updated through activity FIRA24 from case FIR09-00097.
|
Alarm Plan Check | 10/19/2009 | | 10/19/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modification passed.
|
PLANS TAKEN FRONT DESK ALARM | | | 10/19/2009 | | DONE |
|
|
|
Approved plan modification drawings available at front counter
|
Inspection Record Card- Fire | 10/19/2009 | | 10/19/2009 | | DONE |
|
|
|
|
Telephone call | | | 10/19/2009 | | DONE |
|
|
|
t/c w bryan colson at ###-#### - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 10/19/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/19/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/19/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/15/2009 | | |
Barbara Stitt
|
|
|
|
INSP-Alarm Testing | 10/9/2009 | 10/9/2009 | 10/9/2009 | A | PASS |
Troy Cobbley
|
|
|
The sync issue between the common area a/v's and the handi-cap room a/v's has been resolved and tested ok. Waiting on the resubmittals showing this work and the resolution with the atrium.
|
Telephone call | | | 10/6/2009 | | DONE |
|
|
|
Spoke with Michael Dillon (Dillon Consulting Engineers) who prepared the Smoke Management System Engineering Report. I referenced page 5 of the report, specifically the fourth paragraph detailing the planters and associated protection requirements. He clarified that he did, in fact, intend 30" planter width to mean 'width' and not 'length', as in, extend a minimum of 30" into the atrium area. He also clarified that the smoke detectors and sprinkler heads specified in his report as being needed in the planters are definately required due to the issues described in his report. SUMMARY: The planters are required to extend a minimum of 30" into the atrium; sprinklers and smoke detectors are required in those planters as specified in the report.
|
Telephone call | | | 10/6/2009 | | DONE |
|
|
|
Spoke withMichael Pemberton of Big M Electric regarding the plan modifications submitted on 10/2/09. The title block indicates 'as-built', however there are multiple items from previous reviews that were not addressed as well as the atrium smoke shutter documentation. I explained to him that I spoke with the engineer (see additional phone call activity) and verified that smoke detectors will need to be added to the planters specified in the smoke control report dated November 20, 2007. I gave him two options: 1) I will cross out the 'as-built' description on the plans, soley review them based on the shutter additions, and then he would need to submit again prior to calling for a final inspection with all of the changes incorporated into the drawings, thus paying any additional plan review fees; or 2) I can fail these submitted drawings and he can resubmit prior to calling for a final inspection will all changes incorporated that reflect the true as-built information including but not limited to the shutter information, additional smoke detectors in the atrium planters, room changes, previous review comments, etc..) thus paying only one set of review fees. He opted for the second option.
|
1st review completed | | | 10/6/2009 | | DONE |
|
|
|
|
Alarm Plan Check | 10/6/2009 | | 10/6/2009 | | FAIL |
Stephanie L. Cobbley
|
|
|
Drawings are intended to be as-built, however do not reflect all as-built information (see phone call activities for further information). The contractor is aware that a resubmittal is required.
|
Plan resubmittals received | | | 10/2/2009 | | |
Tisha Gallop
|
|
|
Plan Modification: received one copy of application and checklist, three copies of submittal documents and full set of plans; taken to fire review
|
INSP-Alarm Testing | 10/1/2009 | 10/1/2009 | 10/1/2009 | P | PASS |
Troy Cobbley
|
|
|
All of the smoke alarms were tested today as well as all of the fire sprinkler to fire alarm panel interconnections. There are two items left that need addressed. They are the shutters on the third floor atrium and the non-syncing of the horn/strobes in the first floor common areas and the handi-cap rooms.
|
INSP-Final Inspection | 9/29/2009 | 9/30/2009 | 9/30/2009 | A | FAIL |
Troy Cobbley
|
|
|
The smoke duct detectors for hvac shutdown and the fire/smoke dampers passed inspection today. Also the hood suppression system interconnection passed inspection. The 14ga wire has been installed at the NAC panels as well.
|
INSP-Final Inspection | 9/28/2009 | 9/29/2009 | 9/29/2009 | A | FAIL |
Troy Cobbley
|
|
|
The inspection continued today. Items left to test include the hood suppression system, hvac shutdown, EOL voltage drop, smoke alarms, smoke shutters/atrium smoke detectors and sprinkler system interconnections. Notification and initiating (smoke detectors/pull stations) were tested on all floors. Two were repaired while I waited.
|
INSP-Final Inspection | 9/25/2009 | 9/28/2009 | 9/28/2009 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for the initiating devices tested today as marked in red. The phone lines and supervision of the NAC panels were verified. One 16ga wire needs to be changed to 14ga as discussed and atrium smoke shutter sequence of operation needs to be verified since it has not been programmed per the approved drawings.
|
INSP-Alarm Testing | 7/6/2009 | 7/7/2009 | 7/7/2009 | A | PASS |
Troy Cobbley
|
|
|
The rough-in inspection for the riser room is passed.
|
INSP-Alarm Testing | 7/1/2009 | 7/1/2009 | 7/1/2009 | P | PASS |
Troy Cobbley
|
|
|
The fire alarm rough-in for the first floor passed.
|
INSP-Alarm Testing | 6/24/2009 | 6/24/2009 | 6/24/2009 | P | PASS |
Troy Cobbley
|
|
|
The fire alarm rough-in for the second floor passed. One smoke detector appears to be overspaced from the east fire doors and will be verified at the final.
|
Telephone call | | | 6/23/2009 | | DONE |
|
|
|
The contractor called regarding smoke detector placement questions. The area in question is on sheet FA1.1.1 Dining 168. Apparently, there is a beam that is 18" deep that runs East-to-West. The ceiling height is 17.9'. Per NFPA 72, if the beam depth does not exceed 10% of the ceiling height, then it can be treated as a smooth ceiling, otherwise smoke detectors will need to be added to cover the 'pocket' created by the beam. In addtion, the contractor stated that there are dormers around the fireplace that did exceed the 10%. I indicated that based on his description that smoke detectors would need to be placed in the 'pocket' created by the dormers.
|
INSP-Alarm Testing | 6/9/2009 | 6/9/2009 | 6/10/2009 | P | DONE |
Troy Cobbley
|
|
|
This was a rough-in inspection for the center building third floor fire alarm system which passed.
|
INSP-Alarm Testing | 4/8/2009 | 4/8/2009 | 4/9/2009 | P | CANC |
Troy Cobbley
|
|
|
The wrong inspection number was called in.
|
INSP-Sprinkler Rough-in | 4/6/2009 | 4/6/2009 | 4/7/2009 | P | CANC |
Troy Cobbley
|
|
|
wrong permit called in.
|
Issue and Print Permit | | | 3/9/2009 | | |
Barbara Stitt
|
|
|
|
Plan assigned to (Stephanie) | 2/26/2009 | | 3/5/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 3/5/2009 | | 3/5/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See redlined plans and review comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2009 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 3/5/2009 | | 3/5/2009 | | DONE |
|
|
|
|
Telephone call | | | 3/5/2009 | | DONE |
|
|
|
t/c w michael pemberton at ###-#### - permit ready and no fees due
|
Permit Ready to Issue | | | 3/5/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/26/2009 | | |
Stephanie L. Cobbley
|
|
|
received application, letter from Curry Architecture, product info, plan sheets A1.1, FA0, FA0.1, FA0.2, FA0.3, FA1.1, FA1.1.1, FA1.1.2, FA1.1.3, FA1.2, FA1.2.1, FA1.2.2, FA1.2.3, FA2.1, FA2.1.1, FA2.1.2, FA2.1.3, FA2.2, FA2.2.1, FA2.2.2, FA2.2.3, FA3.1, FA3.1.1, FA3.1.2, FA3.1.3, FA3.2, FA3.2.1, FA3.2.2, FA3.2.3, FA4, FA5, FA6.1, FA6.2, FA7; taken to Fire Review
|
Plan assigned to (Stephanie) | 1/28/2009 | | 2/12/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 2/12/2009 | | 2/11/2009 | | FAIL |
Stephanie L. Cobbley
|
|
|
see review comments and redlined plans
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2009 | | DONE |
|
|
|
denied plans available for pick up
|
Miscellaneous action | | | 2/11/2009 | | DONE |
|
|
|
faxed comments to contractor
|
Application received | | | 1/28/2009 | | |
|
|
|
|