Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR09-00115
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 833 W DIAMOND ST
Project NameECCO ELECTRONICS
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of dropping sprinklers below a new ceiling with arm overs.

(ECCO) Remodel to a portion of the existing 40,335 square foot first floor and a first time tenant improvement to the 9,230 square foot second floor. NOTE: This building is fully fire sprinklered for area increase. Work to the first floor to include: Adding new elevator, elevator equipment room constructed of 8" concrete smooth surface block on the exterior of the building , new Concore 2500 Access floor panel system in the server room, extending the existing server room walls to the underside of the second floor, construction of new walls for a lab area with a new door/tempered window, construction of new walls for a break room, and other misc. work per the plans. Work to the second floor to include: Construction of new walls for a new conference room, offices, mail room, smaller conference room, corridor with a breakroom/coffee station, one men's restroom, one women's restroom, one unisex restroom, and second floor framing construction for new HVAC and janitor/storage rooms. Second floor misc. work to include: New glass handrail, relocating a ducting chase, modifying the vestibule ceiling, slopeing gypcrete flooring down to plywood floor landings at both stairs, and adding office cubicels. All work per approved plans, Engineering, attached Plan review report, and CZC08-00167. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/6/20095/7/20095/7/2009APASS
DetailsForrest France
Corrections verified for completion, fire sprinkler permit finaled.
INSP-Final Inspection5/6/20095/6/20095/6/2009AFAIL
DetailsForrest France
Mixed response heads at the 2nd level ceiling above the front entry area need to match remainder of quick response heads provided at the remodel area.
Pending Assignment by SAM2/5/2009 4/21/2009 DONE
DetailsSteve Munroe
4/21/2009 15:23:27 ALR - activity updated through activity FIRA158 from case FIR09-00259.
INSP-Sprinkler Rough-in/Hydro4/9/20094/10/20094/10/2009APART
DetailsForrest France
Need resubmitted plans for modifications at the new lunchroom, mech. room, and elevator pit, noted one missing retaining strap. Missing hanger per previous inspection installed.
INSP-Supply line flush3/9/20093/10/20093/10/2009APASS
DetailsTroy Cobbley
This inspection was not for a flush but actually a cover inspection for the remaining sprinkler piping on the second floor. THe piping is ok to cover. Work is not complete in the mechanical room or in the elevator shaft which is not shown on this seto of sprinkler plans.
INSP-Sprinkler Rough-in2/10/20092/11/20092/11/2009APART
DetailsTroy Cobbley
See the city approved plans for the hardlid areas that are ok to cover
Issue and Print Permit  2/9/2009 DONE
Telephone call  2/6/2009  
DetailsCathy Brown
tlk to commercial fire for brooks ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  2/6/2009 DONE
DetailsCathy Brown
Plan assigned to (Tim)2/5/2009 2/5/2009 DONE
DetailsTim Frost
Ecco
Inspection Record Card- Fire2/5/2009 2/5/2009 DONE
DetailsCathy Brown
Application received  2/5/2009