Miscellaneous action | | | 7/17/2009 | | DONE |
|
|
|
Taken to records for scanning.
|
INSP-Final Inspection | 6/15/2009 | 6/16/2009 | 6/18/2009 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 6/12/2009 | 6/15/2009 | 6/15/2009 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for the location where one horn/strobe failed to operate. The candella had to be changed on three others while I waited. A re-inspection fee has been applied.
|
INSP-Final Inspection | 6/10/2009 | 6/12/2009 | 6/12/2009 | A | CANC |
Troy Cobbley
|
|
|
Cancelled per Robert due to needing to charge batteries for the FACP. To be rescheduled for Monday
|
(F) Reprint permit | | | 6/9/2009 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/9/2009 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/29/2009 | | 5/29/2009 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 5/29/2009 | | DONE |
|
|
|
Left a voice message for Charlie and told him that permit is ready & fees due///5-29-09 @ 9:30am BAS
|
Permit Ready to Issue | | | 5/29/2009 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 5/8/2009 | | 5/28/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
5/28/2009 13:46:38 SLC - activity updated through activity FIRA24 from case FIR09-00120.
|
Alarm Plan Check | 5/28/2009 | | 5/28/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 5/28/2009 | | DONE |
|
|
|
Approved plans available at front counter
|
Plan resubmittals received | | | 5/8/2009 | | |
Tisha Gallop
|
|
|
Plan Modification: Received application, submittal folder and plans sheets 1,2,3,4,5,6; taken to fire review
|
INSP-Final Inspection | 4/17/2009 | 4/20/2009 | 4/20/2009 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with sam rogers permission. The items that were tested and passed today were the phone lines from the existing silent knight panel to the central station, a trouble signale from the new panel to the silent knight panel, tamper switch, PIV switch, flow switch and hvac shutdown from the activation of one smoke detector. No other items were inspected. The other items will be inspected when the monitoring agreement is complete and the existing silent knight panel is removed and the phone lines attached to the new simplex panel.
|
INSP-Final Inspection | 4/16/2009 | 4/17/2009 | 4/17/2009 | P | FAIL |
Troy Cobbley
|
|
|
Todays test was to be for only the riser monitoring portion of the system. Test had to be failed due to the central station not receiving all of the signals such as phone line 1 and 2 troubles. Per Robert this test will be rescheduled for monday.
|
Inspection Record Card- Fire | 2/24/2009 | | 2/24/2009 | | DONE |
|
|
|
|
Telephone call | | | 2/24/2009 | | DONE |
|
|
|
t/c w charlie at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 2/24/2009 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/24/2009 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 2/9/2009 | | 2/23/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 2/23/2009 | | 2/23/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See review comments and redlines
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/23/2009 | | DONE |
|
|
|
Approved plans taken to front counter at 5pm
|
Case Summary | | | 2/9/2009 | | DONE |
|
|
|
|
Application received | | | 2/9/2009 | | |
|
|
|
|