Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR09-00125
StatusFinaled
Name CURTIS FIRE SPRINKLER SERVICE INC
Site Address 8783 W HACKAMORE DR
Project NameSIMPLEX/GRINNELL
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of changing the warehouse to extra hazard group II for storage of plastic below 12'. In addition, the office area is being renovated. The building is stated as being of TJI and wood joist construction.

(SIMPLEX/GRINNELL) NOTE: This building is fully fire sprinklered for area increase. To finish a new 7,723 sq. ft. office tenant with 1,950 sq. ft. of assembly Conference/Training room and 4,937 sq.ft. of warehouse in a existing 14,965 sq.ft. building. Interior demolition permit done under BLD08-02171. Work to include: construction of new interior partitions, door installations, suspended ceiling work, engineered folding wall, wall covering, window blinds, installation of shelving, cabinets, and partitions supplied by owner to create a work areas, warehouse, storage, conference, break room, and office areas. All work per the approved plans, plan review report, adopted codes, and city ordinances. NOTE: A Certificate of Occupancy is to be issued when completed and approved. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/21/20094/21/20094/21/2009PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro4/9/20094/9/20094/9/2009PPASS
DetailsTroy Cobbley
The overhead hydro test passed.
INSP-Sprinkler Rough-in/Hydro4/8/20094/8/20094/8/2009PFAIL
DetailsTroy Cobbley
The above ground hydro test failed.
INSP-Sprinkler Rough-in/Hydro4/6/20094/6/20094/6/2009AFAIL
DetailsTroy Cobbley
The overhead hydro test failed due to atleast two observed leaks/puddles on the floor.
INSP-Sprinkler Rough-in/Hydro4/2/20094/3/20094/3/2009PPART
DetailsTroy Cobbley
The overhead hydro test failed. The sprinkler piping rough-in passed. There were acouple of corrections items that have been marked on the city approved plans that will be verified at the final.
Issue and Print Permit  3/9/2009 DONE
Sprinkler Plan Check3/3/2009 3/3/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  3/3/2009 DONE
DetailsTim Frost
Inspection Record Card- Fire3/3/2009 3/3/2009 DONE
Details
Telephone call  3/3/2009 DONE
Details
t/c w don curtis at ###-#### - permit ready and fees given
Permit Ready to Issue  3/3/2009 DONE
Details
Sprinkler Plan Check2/26/2009 2/26/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Miscellaneous action  2/26/2009 DONE
DetailsTisha Gallop
applicant picked up failed plans
Plan resubmittals received  2/26/2009  
DetailsTim Frost
Received application and four copies of submittal package and plan sheets FP-01; taken to Fire Review
Plan resubmittals received  2/20/2009 DONE
received resubmittal application , docs and 4 copies of sheet FP-01 of 1 sent to fire.
Sprinkler Plan Check2/18/2009 2/18/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Telephone call  2/18/2009 DONE
Details
left vm for don at ###-#### - permit has been rejected - needs to be picked up and resubmitted
Application received  2/12/2009  
Case Summary  2/12/2009 DONE
INSP-Sprinkler Rough-in/Hydro4/7/20094/7/2009 A 
Details
Scheduled by a contractor via Hello! on 4/7/2009 at 7:03:09 AM. Contact: ###-####.
Pending Assignment by SAM2/12/2009