Miscellaneous action | | | 5/11/2009 | | DONE |
|
|
|
Plans taken to records to scan
|
INSP-Final Inspection | 3/26/2009 | 3/26/2009 | 3/27/2009 | P | PASS |
Forrest France
|
|
|
C/N issues completed, fire alarm retest passed, pemit finaled.
|
INSP-Final Inspection | 3/25/2009 | 3/25/2009 | 3/25/2009 | P | FAIL |
Forrest France
|
|
|
Notification appliances are not in synchronization as required per NFPA 72, sprinkler tamper and waterflow signals are not descripted correctly at the supervising station-need accurate account information for tamper, supervisory and alarm signals. Remainder of testing completed okay including FACP, SD, MP, etc.
|
INSP-Final Inspection | 3/19/2009 | 3/20/2009 | 3/20/2009 | A | NR |
Forrest France
|
|
|
Work is not ready for final inspection per phone call from alarm contractor (Matt ###-####).
|
Issue and Print Permit | | | 3/17/2009 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 3/3/2009 | | 3/16/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 3/16/2009 | | 3/16/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See redlined plans and review comments
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2009 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 3/16/2009 | | 3/16/2009 | | DONE |
|
|
|
|
Telephone call | | | 3/16/2009 | | DONE |
|
|
|
t/c w matt clark at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/16/2009 | | DONE |
|
|
|
|
Application received | | | 3/3/2009 | | |
|
|
|
|