Miscellaneous action | | | 12/1/2010 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 11/9/2010 | 11/10/2010 | 11/10/2010 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
FIR-Aging Inspection | 11/5/2010 | 11/5/2010 | 11/9/2010 | | NR |
Troy Cobbley
|
|
|
work is in progress. See entry for 11/9/10
|
INSP-Final Inspection | 11/8/2010 | 11/9/2010 | 11/9/2010 | A | FAIL |
Troy Cobbley
|
|
|
Everything worked except the tamper switch closest to the riser was not adjusted correctly.
|
INSP-Final Inspection | 4/1/2010 | 4/2/2010 | 4/2/2010 | P | FAIL |
Troy Cobbley
|
|
|
We verified the Netcon rating at the beginning of the inspection and found that it got only a 6. U.L. listing is for a 5 or less. No other items inspected.
|
Issue and Print Permit | | | 3/30/2010 | | DONE |
|
|
|
|
Miscellaneous action | | | 3/29/2010 | | DONE |
|
|
|
requested documentation recieved from contractor
|
Alarm Plan Check | 3/29/2010 | | 3/29/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
see review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 3/29/2010 | | DONE |
|
|
|
approved plans available at front counter
|
Inspection Record Card- Fire | 3/29/2010 | | 3/29/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 3/29/2010 | | DONE |
|
|
|
t/c w lori at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/29/2010 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 3/16/2009 | | 3/29/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
3/29/2010 14:11:20 SLC - activity updated through activity FIRA24 from case FIR09-00173.
|
Telephone call | | | 3/26/2010 | | DONE |
|
|
|
Let Alarmco know they still need to provide a pull station for this sprinkler monitoring panel, show it on the one-line, and to provide data sheets for the pull station and FACP, battery calculations, and an operations matrix. I let them know that I would not reject the plans if I could get the information by Monday (3/29/10) morning.
|
Plan resubmittals received | | | 3/23/2010 | | |
Barbara Stitt
|
|
|
|
Telephone call | | | 3/16/2010 | | DONE |
|
|
|
Spoke to Lori asking about the status of this project and that we are still waiting for resubmittals. She stated she would need to talk to Bill and would get back to me.
|
Miscellaneous action | | | 3/30/2009 | | DONE |
Tisha Gallop
|
|
|
picked up failed plans
|
1st review completed | | | 3/25/2009 | | FAIL |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 3/25/2009 | | 3/25/2009 | | FAIL |
Stephanie L. Cobbley
|
|
|
See review comments. Denied plans available at front counter for pick up
|
Miscellaneous action | | | 3/25/2009 | | DONE |
|
|
|
Review comments faxed to contractor
|
Case Summary | | | 3/16/2009 | | DONE |
|
|
|
|
Application received | | | 3/16/2009 | | |
|
|
|
|