INSP-Final Inspection | 5/28/2009 | 5/29/2009 | 5/29/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 5/29/2009 | | DONE |
Tim Frost
|
|
|
Contractor changed the backflow preventer from a 3" to a 4". The manufacturer was the same Wilkings. The 4" has less friction loss than the 3". Therefore the change is APPROVED.
|
INSP-Final Inspection | 5/27/2009 | 5/28/2009 | 5/28/2009 | P | FAIL |
Troy Cobbley
|
|
|
The alarm interconnections need to be tested. The forward flush of the backflow needs to be performed. The backflow as installed does not match the riser detail on the city approved drawings. Contact the plan reviewer to verify if the new backflow will be adequated to remain. Contractor still needed to install a sidewall sprinkler head.
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2009 | 5/20/2009 | 5/20/2009 | P | PASS |
Troy Cobbley
|
|
|
The above ground hydro test passed. The sprinkler piping above the layin tile can be coverd.
|
INSP-Sprinkler Rough-in | 4/29/2009 | 4/30/2009 | 4/30/2009 | A | PASS |
Troy Cobbley
|
|
|
The piping above the mezzanine can be covered. The insulation is not completely installed and will require another inspection. I found where the AP upright sprinkler heads are not within their listed distance from the deck, 1"-3", as per the data sheet. Also the AP heads need to be within 5'-0" of the exterior walls as per the detail provided on the city approved plans. The insulation is blocking the spray of the upright heads beneath the mezzanine as well.
|
INSP-Sprinkler Rough-in | 4/23/2009 | 4/23/2009 | 4/23/2009 | P | PART |
Troy Cobbley
|
|
|
See the city approved plans for the piping locations above the hard lid ceilings that are ok to cover. Per discussion with Leroy and Christina the remaining rough-in inspection will be called in next week when the earthquake bracing, wire branchline restraints and insulation at the deck have been installed.
|
Issue and Print Permit | | | 4/23/2009 | | DONE |
|
|
|
|
Case Summary | | | 4/22/2009 | | |
|
|
|
|
Sprinkler Plan Check | 4/22/2009 | | 4/22/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/22/2009 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 4/22/2009 | | 4/22/2009 | | DONE |
|
|
|
|
Telephone call | | | 4/22/2009 | | DONE |
|
|
|
t/c w bryan at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/22/2009 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/21/2009 | | 4/21/2009 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Telephone call | | | 4/21/2009 | | DONE |
Tim Frost
|
|
|
Called Tyson to ask him where the deflector distance was shown.
Got voice mail and left message
|
Miscellaneous action | | | 4/21/2009 | | DONE |
Tim Frost
|
|
|
Faxed Comments
|
Telephone call | | | 4/21/2009 | | DONE |
|
|
|
t/c w bryan at ###-#### - permit was denied - needs to be picked up and resubmitted
|
Miscellaneous action | | | 4/17/2009 | | DONE |
Tisha Gallop
|
|
|
picked up rejected plans
|
Early Start | | | 4/17/2009 | | DONE |
Tim Frost
|
|
|
Please, see attached comments.
|
Plan resubmittals received | | | 4/14/2009 | | DONE |
|
|
|
received 4 sets of plans /applications sent to fire
|
Sprinkler Plan Check | 4/13/2009 | | 4/13/2009 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Miscellaneous action | | | 4/13/2009 | | DONE |
|
|
|
Faxed review
|
Telephone call | | | 4/13/2009 | | DONE |
|
|
|
t/c w bryan at ###-#### - permit rejected - needs to be picked up and resubmitted
|
Plan resubmittals received | | | 4/9/2009 | | |
Tim Frost
|
|
|
|
Telephone call | | | 4/6/2009 | | DONE |
|
|
|
Spoke with Christine at Horton Construction. Explained that the mezzanine is Ordinary Hazard. That it would require 60 min construction in order to comply with NFPA 13. I told her that I gave Shilo two options. One to enclose the mezzanine with 60 min construction, the second was to use ordinary hazard sprinklers not attic sprinklers since they are only rated for light hazard.
|
Telephone call | | | 4/6/2009 | | DONE |
|
|
|
I spoke with John Menard (Building) he said he did not require anything to enclose the mezzanine. Since NFPA 13 requires 60 min I told Christine that she could use 1 layer of 5/8 type X gypsum board (40 min) on wood studs (20 min) from tables 721.6.2(1) and table 721.6.2(2) which would yield 60 min. There will be sprinklers inside and outside of the space.
|
Sprinkler Plan Check | 4/2/2009 | | 4/2/2009 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Telephone call | | | 4/2/2009 | | DONE |
|
|
|
t/c w bryan at ###-#### - permit was denied - needs to be picked up and resubmitted
|
Plan resubmittals received | | | 3/27/2009 | | DONE |
|
|
|
received 1 transmittal letter, and 4 permit applications and 4 sets of plans taken to Tim F. in fire.
|
Miscellaneous action | | | 3/20/2009 | | DONE |
Tisha Gallop
|
|
|
picked up failed plans
|
Plan assigned to (Tim) | 3/18/2009 | | 3/19/2009 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/19/2009 | | 3/19/2009 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Miscellaneous action | | | 3/19/2009 | | DONE |
Tim Frost
|
|
|
Emailed Comments
|
Telephone call | | | 3/19/2009 | | DONE |
|
|
|
t/c w tyson smith at ###-#### - permit was rejected - needs to be picked up and resubmitted
|
Application received | | | 3/18/2009 | | |
|
|
|
|
Pending Assignment by SAM | 3/18/2009 | | 3/18/2009 | | DONE |
Tim Frost
|
|
|
3/18/2009 15:40:17 TRF - activity updated through activity FIRA158 from case FIR09-00179.
|