Miscellaneous action | | | 6/3/2009 | | DONE |
|
|
|
Taken to records for scanning
|
INSP-Final Inspection | 5/15/2009 | 5/15/2009 | 5/15/2009 | P | PASS |
Forrest France
|
|
|
Remaining two correction notice items completed, contractor to provide signals list and offsite account information for verification as discussed to PDS fire office.
|
INSP-Alarm Testing | 5/13/2009 | 5/14/2009 | 5/14/2009 | A | FAIL |
Forrest France
|
|
|
Duct detector at the conference room 2nd floor needs to shut down power to the HVAC unit immediately upon smoke detection, missing mag lock interconnection relay to drop power to the door locks upon fire alarm activation.
|
INSP-Final Inspection | 5/12/2009 | 5/13/2009 | 5/13/2009 | A | FAIL |
Forrest France
|
|
|
Duct detector at the conference room failed to shut down power to the HVAC unit, DD at the mechanical room programed incorrectly, horns and strobes are not in sync. on the 1st or 2nd floors, fire hat at the elevator is not repaired, reinspection fees will apply.
|
INSP-Final Inspection | 5/5/2009 | 5/6/2009 | 5/6/2009 | A | FAIL |
Forrest France
|
|
|
All three duct detectors failed to shut down HVAC units, notification devices at the second floor are not in sync, elevator hat does not flash upon machine room initiating device activation, voltage monitor for shunt trip is not provided for at the FACP, missing notification at one conference room on the 1st floor, overspacing at the elevator lobby and breakroom, notification at the 1st floor not tested due to adjustments to be made.
|
CHANGE STATUS TO (ISS) | | | 4/23/2009 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/23/2009 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 4/20/2009 | | 4/22/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
4/22/2009 15:47:18 SLC - activity updated through activity FIRA24 from case FIR09-00182.
|
Alarm Plan Check | 4/22/2009 | | 4/22/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
Plan modification approved - drawings and submittals are not to replace the existing approved plans. The plan modification documents are to be supplementary.
|
PLANS TAKEN FRONT DESK ALARM | | | 4/22/2009 | | DONE |
|
|
|
Approved plans available at front counter
|
Plan resubmittals received | | | 4/20/2009 | | |
Tisha Gallop
|
|
|
Plan Modification: Received applicaiton, submittal info, and plan sheets F-1, F-2, F-3; taken to fire review.
|
Issue and Print Permit | | | 4/8/2009 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 3/24/2009 | | 4/7/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
4/7/2009 15:45:14 SLC - activity updated through activity FIRA24 from case FIR09-00182.
|
Alarm Plan Check | 4/7/2009 | | 4/7/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 4/7/2009 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 4/7/2009 | | 4/7/2009 | | DONE |
|
|
|
|
Telephone call | | | 4/7/2009 | | DONE |
|
|
|
t/c w lori at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/7/2009 | | DONE |
|
|
|
|
Case Summary | | | 3/24/2009 | | DONE |
|
|
|
|
Miscellaneous action | | | 3/24/2009 | | DONE |
|
|
|
Approved an early start request
|
Application received | | | 3/24/2009 | | |
|
|
|
|
Reinspection Fee (no hold) | 5/13/2009 | 5/14/2009 | | A | |
Forrest France
|
|
|
See permit activities and fire code review notes for details.
|