INSP-Final Inspection | 5/18/2009 | 5/18/2009 | 5/18/2009 | P | PASS |
Forrest France
|
|
|
Verified new heads have been provided per the plan modification, one missing ceiling tile to be installed prior to BLD final inspection, fire sprinkler permit finaled.
|
Telephone call | | | 5/11/2009 | | DONE |
Tim Frost
|
|
|
Switching to a different sprinkler due to a minimum spacing issue. Please, see attached.
|
INSP-Final Inspection | 5/7/2009 | 5/8/2009 | 5/8/2009 | A | FAIL |
Troy Cobbley
|
|
|
To be rescheduled per the contractor.
|
Plan assigned to (Tim) | 4/8/2009 | | 4/9/2009 | | DONE |
Tim Frost
|
|
|
4/9/2009 08:52:18 SJA - activity updated through activity FIRA22 from case FIR09-00230.
|
Sprinkler Plan Check | 4/9/2009 | | 4/9/2009 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2009 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/9/2009 | | 4/9/2009 | | DONE |
|
|
|
|
Telephone call | | | 4/9/2009 | | DONE |
|
|
|
left vm for jim danes at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 4/9/2009 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/9/2009 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | | 4/8/2009 | | |
|
|
|
|
Case Summary | | | 4/8/2009 | | DONE |
|
|
|
|