Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR09-00264
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 4800 PRODUCTION AVE
Project NameIdaho Timber - Storage Buildin
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of a new dry system to protect a new prefabricate building. The building will be use as wood manufacturing; it will not be used as a saw mill. The hydraulic design area was increased due to a dry system and a slope >2:12. There will be solid pile storage of lumber ? 12' (class II commodity) in height. The building is therefore classified as Ordinary Hazard Group II.

Idaho Timber - Storage Building - **This building is fully Fire Sprinklered** To construct a new, 11,250 square foot, one story, pre-engineered metal storage out building on an existing foundation along with a 114 square foot attached accessory building and a 236 square foot attached accessory building all loss to a previous fire. There is no plumbing work associated with the building. All construction per the Engineering, approved plans, and attached plan review report. Electrical and Fire Sprinkler work requires separate permits. DRH08-00333 per Planning and Zoning. (SRZ)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  1/5/2010 DONE
DetailsTim Frost
Plans taken to scanning.
INSP-Final Inspection11/4/200911/5/200911/5/2009PPASS
DetailsForrest France
On site functional trip testing of the new dry system completed satisfactory, water delivered to the inspectors test at 60 seconds. Final walkthrough passed, permit finaled.
INSP-Final Inspection10/20/200910/20/200910/21/2009PNH
DetailsForrest France
Need the fire sprinkler contractor representative on site to complete functional trip testing of the new dry system valve and appurtenances.
INSP-Sprinkler Rough-in/Hydro6/22/20096/23/20096/23/2009APART
DetailsForrest France
Concluded satisfactory 24 hr. pneumatic testing with allowable pressure loss of 1/2 psi.
INSP-Sprinkler Rough-in/Hydro6/19/20096/22/20096/22/2009APART
DetailsForrest France
Begin 24 hr. air testing for the new dry system at 40.5 psig @ 10:00.
INSP-Sprinkler Rough-in/Hydro6/18/20096/19/20096/19/2009APART
DetailsForrest France
Overhead hydrostatic testing for the new dry system passed, also reinspected C/N items from previous visit.
INSP-Sprinkler Rough-in/Hydro6/18/20096/18/20096/18/2009PFAIL
DetailsForrest France
Correction list includes blocked upright coverage at the equipment room, missing flexible couplings at the feed main through warehouse wall, provide listed air maintenance device, noted dry valve installed does not match type submitted, remote test connection has been relocated from where shown on approved plans.
Issue and Print Permit  5/4/2009 DONE
Plan assigned to (Tim)4/23/2009 5/1/2009 DONE
DetailsTim Frost
5/1/2009 13:52:20 TRF - activity updated through activity FIRA22 from case FIR09-00264.
Sprinkler Plan Check5/1/2009 5/1/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  5/1/2009 DONE
DetailsTim Frost
Inspection Record Card- Fire5/1/2009 5/1/2009 DONE
Details
Telephone call  5/1/2009 DONE
Details
left message w bobbi for brook at ###-#### - permit ready and fees given
Permit Ready to Issue  5/1/2009 DONE
Details
Application received  4/23/2009