Miscellaneous action | | | 9/3/2009 | | DONE |
|
|
|
Fire alarm plans taken to records for scanning
|
INSP-Final Inspection | 7/27/2009 | 7/27/2009 | 7/27/2009 | P | PASS |
Forrest France
|
|
|
Notification in areas A and C passed field testing, mag locks at one location tied in and tested while on site, fire alarm permit finaled.
|
INSP-Final Inspection | 7/23/2009 | 7/24/2009 | 7/24/2009 | A | DEFR |
Forrest France
|
|
|
Randy or Kelly ###-#### Phone #: ###-####
|
INSP-Alarm Testing | 7/15/2009 | 7/16/2009 | 7/16/2009 | A | DONE |
Troy Cobbley
|
|
|
Fire alarm system is complete in areas 'B' and 'D'. Un-needed sample tubes from the duct detectors have been removed. However, there are 41 HVAC units with duct detectors but only 39 sample tubes are accounted for. The two missing additional sample tubes will need to be provided prior to final.
|
INSP-Alarm Testing | 7/13/2009 | 7/14/2009 | 7/14/2009 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for areas B and D. Alarms will be complete in these two areas when Alarmco finals their AES system and the samples tubes are installed correctly in the existing duct smoke detectors or verification is provided that this was an exceptable installation at the time the building was built.
|
INSP-Alarm Testing | 7/13/2009 | 7/13/2009 | 7/13/2009 | P | PART |
Troy Cobbley
|
|
|
The fire alarm panel and the interconnection with the NAC in the east end were tested today. The AES system installed by Alarmco was not tested. They were contacted about the importance of getting this inspected right away. The notification devices in areas B and D were tested. The strobe and horns functioned but the WP horn/strobe in the east end of the central garden did not function. Also several strobes are overspaced, see plans, and two additional strobes have been added in the east corridor as marked on the approved plans. No duct smoke detectors have been tested at this time.
|
INSP-Alarm Testing | 7/9/2009 | 7/10/2009 | 7/10/2009 | A | FAIL |
Troy Cobbley
|
|
|
Per the installer, who was not at the project site, the fire alarm system is not ready to test due to an issue with a duct smoke detector. No inspection was performed.
|
Inspection Record Card- Fire | 5/27/2009 | | 5/27/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Telephone call | | | 5/27/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
Talked to Melissa- permit ready, fees given
|
Permit Ready to Issue | | | 5/27/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Issue and Print Permit | | | 5/27/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan assigned to (Stephanie) | 5/12/2009 | | 5/26/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
5/26/2009 15:42:10 SLC - activity updated through activity FIRA24 from case FIR09-00316.
|
Alarm Plan Check | 5/26/2009 | | 5/26/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See redlines and review comments. Contractor to submit plan modification prior to calling for inspection.
|
PLANS TAKEN FRONT DESK ALARM | | | 5/26/2009 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Application received | | | 5/12/2009 | | |
|
|
|
|