Permit Information
Permit NumberFIR09-00317
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 3536 W HILL RD
Project NameHillside Jr. High Locker Room
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of one wet and three dry systems to protect and existing school. There will be a new locker room addition. The existing school currently does not have fire protection except in the basement. The basement system will be connected to the new system upstairs. The building is intended to be fully sprinklered. Extended coverage sidewall, ssp and ssu are being utilized.

(Hillside Junior High - Locker Room Addition & NFPA 13 Fire Suppression / Alarm System) To build a 4,058 sq. ft. locker room addition on the northeast end of the existing 70,641 sq. ft. school building; construction of an 8", 2-hour, masonry fire barrier wall separating the new Type V-B construction from the existing Type VB construction. The new construction will be constructed of non-combustible materials per approved Alternate Request Letter on file, approved by Building Official & Fire Marshall. The entire school (new and existing) will be fully fire sprinklered per NFPA 13 as regulated by the fire department as part of this permit. A Grading & Drainage with site utilities permit is being issued under BLD09-00108. Work includes construction of a reinforced concrete foundation, stem wall, piers, footings and concrete slab; assembly of a pre-manufacture steel building frame with metal skin siding and roofing, construction of reinforced masonry fire barrier wall with protected 90 minute door opening and fire/smoke dampers at duct penetrations at the south end wall and north end steel frame wall, insulation and finishes; fully accessible shower / locker / restrooms for boys and girls; installation of suspended ceiling grid system, electrical, mechanical, plumbing, fire suppression and alarm systems, all per reviewed plans. This lot is within the floodplain area. An elevation certificate has been submitted and accepted by Jim Wylie, Public Works Dept. drs CUP08-00132
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/11/20099/11/20099/11/2009PPASS
DetailsTroy Cobbley
See todays entry for corrections.
INSP-Final Inspection9/10/20099/11/20099/11/2009APASS
DetailsTroy Cobbley
See todays entry for corrections.
INSP-Sprinkler Rough-in/Hydro9/9/20099/11/20099/11/2009APASS
DetailsTroy Cobbley
The 24 hour air test passed on all three dry systems. The trip tests passed on dry system #2 and #3 but failed on system #1. Additional pendants are needed as discussed in the pockets separating the existing gym from the new locker rooms and the missing uprights on system #1 are needed. Per Scott system #1 does not need to be rehydro tested or 24 hour tested.
INSP-Sprinkler Rough-in/Hydro9/9/20099/10/20099/10/2009PPASS
DetailsTroy Cobbley
Start of 24 hour air test at 12:00. The starting pressures have been written on the wall adjacent to the risers with the current air pressure.
INSP-Sprinkler Rough-in/Hydro9/9/20099/10/20099/10/2009APASS
DetailsTroy Cobbley
System #2 passed hydrostatic testing.
INSP-Sprinkler Rough-in/Hydro9/9/20099/9/20099/9/2009PFAIL
DetailsForrest France
System #2 failed hydrostatic test. Systems #1,3, and 4 passed hydrostatic tests.
INSP-Sprinkler Rough-in8/26/20098/27/20098/28/2009APASS
DetailsTroy Cobbley
System 2 was missing sidewall sprinklers. Checked piping suppling below sprinklers for sizing and hangers.

Checked system 3 for head spacing.

Missing sprinkler in room 2

One head needs to be changed from an extended coverage to a regular sprinkler in room 21

System 1 over build area are missing sprinklers.

System 1 missing upright sprinklers near the peak above the catwalk.
INSP-Sprinkler Rough-in8/26/20098/26/20098/26/2009PCANC
DetailsTroy Cobbley
Cancelled due to time constraints.
INSP-Sprinkler Rough-in8/24/20098/24/20098/24/2009PPASS
DetailsTroy Cobbley
The attic portion of system #3 is finished except for verification of correct insulation depth and related sprinkler coverage and the issue with the branchline and main hangers as previously discussed.
INSP-Sprinkler Rough-in8/19/20098/20/20098/21/2009APART
DetailsTroy Cobbley
Inspected system 2 piping in the attic for the protection of the ground floor. Everything seemed ok except for the hanger situation which was added as a separate activity in the case file.

Inspected system 3 for proper sprinkler coverage. Most of the system was ok. Some areas were not complete and marked in red indicated by NR (Not Reviewed) on the job site plans.

Inspected the new addition for cover. All seemed ok except for the door ways leading into the new area. There were doors leading into this area that blocked coverage from the sidewall sprinklers in the gym for the doorways. I was informed that the doors were to be removed. If the doors are not removed than additional sprinklers will be required in both doorways.

Meeting  8/20/2009 DONE
Discussed various hangers options with Trent of Phoenix Fire Protection. Trent indicated that a professional engineer was reviewing the hangers as they are installed. I told him if the engineer was to approved the installation than it would be ok with us, since chapter 9 of NFPA 13 allows for engineering analysis. In addition, I discussed with him installing more hangers on the 4" main in order to limit the point load for each hanger. The other option was to add additional wood below the hangers. I told him the final decision for using additional hangers would rest with the primary inspector Mr. Troy Cobbley or the PDS/Fire Manger Mr. Scott Arellano. However, it sounded like a pracitical solution in my opinion.
INSP-Sprinkler Rough-in8/19/20098/19/20098/19/2009PFAIL
DetailsTroy Cobbley
Todays inspection was a rough-to-cover inspection for system 2 (attic). After arriving at the project I found that the latest city approved plans were not on site for the inspection. Instead of leaving I stayed at the fitters request to inspect the dry pendant spacing below the ceilings. Half of the the classrooms were locked. The classrooms that were open had missing pendant heads and the plastic shipping clips had not been removed from many of the pendants. So I stopped with the below ceiling inspecion. At this time plans arrived and I started the attic inspection. As with the previous inspection upright coverage is missing at overbuild areas, heads are spaced too far off of smoke curtains and shear walls, heads are spaced too close together. Also the hangers do not meet the minimum distance from the bottom of the structural members as required for branchlines and mains per NFPA 13 chapter 9. Also per chapter 9 the minimum member size to hang 4" piping is 4 x 3. 2 x4 are being used. I also noted that the sprinkler piping does not match the plans near the riser.
CHANGE STATUS TO (ISS)  8/19/2009 DONE
Plan assigned to (Tim)8/11/2009 8/13/2009 DONE
DetailsTim Frost
8/13/2009 15:41:00 TRF - activity updated through activity FIRA22 from case FIR09-00317.
Sprinkler Plan Check8/13/2009 8/13/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  8/13/2009 DONE
DetailsTim Frost
Inspection Record Card- Fire8/13/2009 8/13/2009 DONE
Details
Telephone call  8/13/2009 DONE
Details
left vm for don at ###-#### - permit (plan mod) ready and fees given
Permit Ready to Issue  8/13/2009 DONE
Details
INSP-Supply line flush7/30/20097/31/20097/31/2009PPASS
DetailsTroy Cobbley
The underground supply line flush passed inspection.
INSP-Sprinkler Rough-in/Hydro7/30/20097/31/20097/31/2009APASS
DetailsTroy Cobbley
Underground hydro test passed.
INSP-Sprinkler Rough-in7/23/20097/24/20097/24/2009APART
DetailsForrest France
Underground fire supply line approved for cover, need to install cap or blind flange at the riser stub.
INSP-Sprinkler Rough-in7/21/20097/22/20097/22/2009APART
DetailsTroy Cobbley
The rough-in for system #3 was completed. See the city approved plans for locations of deficiencies.
Sprinkler Plan Check7/10/2009 7/10/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  7/10/2009 DONE
DetailsTim Frost
Inspection Record Card- Fire7/10/2009 7/10/2009 DONE
Details
Telephone call  7/10/2009 DONE
Details
t/c w don weland at ###-#### - permit ready and fees given
Permit Ready to Issue  7/10/2009 DONE
Details
Issue and Print Permit  7/10/2009 DONE
Plan resubmittals received  7/8/2009 DONE
DetailsAlexandra L. DeYoung
rec'd three copies of submittal packets
Miscellaneous action  7/8/2009 DONE
DetailsTim Frost
Email, see attached
Sprinkler Plan Check7/2/2009 7/2/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Miscellaneous action  7/2/2009 DONE
Emailed comments
Telephone call  7/2/2009 DONE
Details
t/c w don weland at ###-#### - permit denied - needs to be picked up and resubmitted
Plan resubmittals received  7/1/2009  
DetailsTim Frost
Rec'd 3 copies of plans and 3 copies of submittal packets
Sprinkler Plan Check6/18/2009 6/18/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Telephone call  6/18/2009 DONE
Details
left vm for don at ###-#### - permit denied - needs to be picked up and resubmitted
Plan resubmittals received  6/12/2009  
DetailsTim Frost
Rec'd 3 copies- taken to Tim
Plan assigned to (Tim)5/22/2009 5/27/2009 DONE
DetailsTim Frost
Sprinkler Plan Check5/27/2009 5/27/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Telephone call  5/27/2009 DONE
DetailsBarbara Stitt
Called and spoke with trent and told him that plans were denied///5-27-09 @ 3:36pm BAS
Plan resubmittals received  5/22/2009 DONE
DetailsAlexandra L. DeYoung
Rec'd 3 copies of application, submittal info, and plans- taken to fire review
Plan assigned to (Tim)5/13/2009 5/15/2009 DONE
DetailsTim Frost
05-27-09 New
Sprinkler Plan Check5/15/2009 5/15/2009 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Meeting  5/15/2009 DONE
DetailsTim Frost
Gave denined plans back to contractor. Discuss the various problems with the plans. Marked up one set of plans for his reference.
Application received  5/13/2009  
Meeting  5/13/2009 DONE
DetailsTim Frost
Intake meeting to go over plans with contractor.