Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberFIR09-00345
StatusFinaled
Name WESTERN STATES FIRE PROTECTION
Site Address 1444 S ENTERTAINMENT AVE Unit: 315
Project NameSTEVENS HENAGER COLLEGE
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of a finish out from a shell. New sprinklers will be armed over and dropped to accommodate the new wall and ceiling configuration. This renovation is under two permits. The permit for suite 305 is under FIR09-00346. The existing system is shown as a 3"x2½"x 1¼" Grid

(STEVENS-HENAGER COLLEGE - 3rd Floor - East Suite #315) For a first time minor tenant improvement on the third floor of an existing shell building. This Office tenant space has a total of 2712 square feet and will consist of open office area, a reception area, and two entry/exit points with work to include: remove door frame and portions of walls for new doors, relocate existing fire extinguisher cabinet, construction of interior office walls, installation of acoustical suspended ceiling, HVAC/mechanical work, electrical work, and misc. interior finish work. The core areas of this floor were finished under the shell and core permit (BLD06-01621). Sprinklers were used for height and story increase. This building is fully sprinklered. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA13 as regulated by the Boise City Fire Department. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/15/20097/16/20097/16/2009APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection7/15/20097/15/20097/15/2009PCANC
DetailsTroy Cobbley
Cancelled due to time constraints. Rescheduled for tomorrow with life safety inspection.
Sprinkler Plan Check7/15/2009 7/15/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  7/15/2009 DONE
DetailsTim Frost
CHANGE STATUS TO (ISS)  7/15/2009 DONE
(F) Reprint permit  7/15/2009 DONE
INSP-Final Inspection7/13/20097/14/20097/14/2009AFAIL
DetailsTroy Cobbley
The scope of work should actually state work in suites 315 and 325. As per telephone discussions between myself, Tim and Eddy with Western States plans need to be resubmitted deleting suite 325 from the scope of work since this area is going to be on hold. All work in suite 315 is complete and the permit can be finaled when the revised scope of work is issued.
INSP-Sprinkler Rough-in7/9/20097/9/20097/9/2009PPASS
DetailsTroy Cobbley
The sprinkler piping, as marked on the plans with todays date, can be covered.
Permit Ready to Issue  6/1/2009 DONE
Inspection Record Card- Fire6/1/2009 6/1/2009 DONE
DetailsBarbara Stitt
Telephone call  6/1/2009 DONE
Called and left message that permit is ready 6-1-09 @ 10:20am BAS
Issue and Print Permit  6/1/2009 DONE
DetailsAlexandra L. DeYoung
Application received  5/29/2009  
Plan assigned to (Tim)5/29/2009 5/29/2009 DONE
DetailsTim Frost
5/29/2009 14:56:42 TRF - activity updated through activity FIRA22 from case FIR09-00345.
Sprinkler Plan Check5/29/2009 5/29/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  5/29/2009 DONE
DetailsTim Frost
1st review completed  5/29/2009 DONE
DetailsTim Frost