Miscellaneous action | | | 1/5/2010 | | DONE |
Tim Frost
|
|
|
Plans taken to scanning.
|
INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit final approved.
|
INSP-Final Inspection | 12/28/2009 | 12/28/2009 | 12/28/2009 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work passed final inspection.
|
INSP-Final Inspection | 12/21/2009 | 12/22/2009 | 12/22/2009 | P | NR |
Forrest France
|
|
|
Painted heads need replaced, riser supervision is incomplete.
|
INSP-Sprinkler Rough-in/Hydro | 12/21/2009 | 12/22/2009 | 12/22/2009 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic retest passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/18/2009 | 12/18/2009 | 12/21/2009 | A | FAIL |
Forrest France
|
|
|
Overhead hydrostatic test failed due to pressue loss at the guage.
|
INSP-Sprinkler Rough-in/Hydro | 12/16/2009 | 12/17/2009 | 12/17/2009 | A | FAIL |
Forrest France
|
|
|
Overhead hydrostatic testing failed due to pressure loss at the guage and visible leakage at two locations.
|
INSP-Sprinkler Rough-in/Hydro | 12/14/2009 | 12/16/2009 | 12/16/2009 | A | NR |
Forrest France
|
|
|
Hydro - Contact: Todd Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley NOTE: Not ready for inspection per contractor- to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 12/14/2009 | 12/17/2009 | 12/16/2009 | A | CANC |
Forrest France
|
|
|
Final - Contact: Todd Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in | 12/14/2009 | 12/15/2009 | 12/15/2009 | P | FAIL |
Forrest France
|
|
|
Inspection for overhead cover at the drop ceilings in the corridors and adjacent rooms failed due to some items including missing seismic bracing, one blocked upright, two areas missing coverage, one mixed head, one upright to be relocated- see plans for red-lines.
|
INSP-Sprinkler Rough-in | 10/23/2009 | 10/23/2009 | 10/23/2009 | P | PART |
Forrest France
|
|
|
Todd Phone#: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 10/20/2009 | 10/21/2009 | 10/21/2009 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at the sheetrock ceiling above the reception desk is okay for cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2009 | 10/14/2009 | 10/14/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas marked in red with todays date where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 10/5/2009 | 10/5/2009 | 10/5/2009 | P | PART |
Forrest France
|
|
|
Okayed for cover as marked on approved plan set.
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2009 | 9/18/2009 | 9/18/2009 | A | PART |
Forrest France
|
|
|
Inspection for overhead cover okayed for the boy's restroom only, HVAC ducting at the girls restroom side obstructs coverage at one upright.
|
Issue and Print Permit | | | 6/22/2009 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/19/2009 | | 6/19/2009 | | DONE |
|
|
|
|
Telephone call | | | 6/19/2009 | | DONE |
|
|
|
t/c w randy bowron - ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/19/2009 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 6/18/2009 | | 6/18/2009 | | DONE |
Tim Frost
|
|
|
6/18/2009 15:53:32 TRF - activity updated through activity FIRA22 from case FIR09-00364.
|
Sprinkler Plan Check | 6/18/2009 | | 6/18/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2009 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 6/17/2009 | | |
Tim Frost
|
|
|
Rec'd three copies of plans and submittal book- taken to Tim Frost
|
Miscellaneous action | | | 6/16/2009 | | |
|
|
|
picked up denied pland
|
Plan assigned to (Tim) | 6/8/2009 | | 6/11/2009 | | DONE |
Tim Frost
|
|
|
6/11/2009 13:27:50 TRF - activity updated through activity FIRA22 from case FIR09-00364.
|
Sprinkler Plan Check | 6/11/2009 | | 6/11/2009 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 6/11/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2009 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 6/11/2009 | | DONE |
|
|
|
left vm for randy bowron - ###-#### - permit denied - needs to be picked up and resubmitted
|
Miscellaneous action | | | 6/11/2009 | | DONE |
Tim Frost
|
|
|
Emailed review to DeBest
|
Application received | | | 6/8/2009 | | |
|
|
|
|