Miscellaneous action | | | 1/5/2010 | | DONE |
Tim Frost
|
|
|
Taken to scanning
|
INSP-Final Inspection | 11/23/2009 | 11/23/2009 | 11/23/2009 | P | PASS |
Forrest France
|
|
|
Permit approved for final status per activity notes completed 9/16.
|
INSP-Final Inspection | 9/16/2009 | 9/16/2009 | 9/16/2009 | P | PASS |
Forrest France
|
|
|
Fire sprinkler final inspection is satisfactory.
|
INSP-Final Inspection | 9/15/2009 | 9/15/2009 | 9/15/2009 | P | NR |
Forrest France
|
|
|
Not ready for final inspection. Ceiling tiles not installed at all sprinklers and multiple sprinklers missing escushions and/or concealer covers.
|
INSP-Sprinkler Rough-in/Hydro | 8/31/2009 | 8/31/2009 | 8/31/2009 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed satisfactory.
|
INSP-Sprinkler Rough-in | 8/26/2009 | 8/27/2009 | 8/28/2009 | A | PART |
Forrest France
|
|
|
Fire sprinkler system modifications for the scope of work are approved for cover per inspection completed by T. Frost, contractor was notified a hydrostatic test will be necessary due to over 20 heads affected.
|
Plan assigned to (Tim) | 8/14/2009 | | 8/19/2009 | | DONE |
Tim Frost
|
|
|
8/19/2009 10:02:15 TRF - activity updated through activity FIRA22 from case FIR09-00485.
|
Sprinkler Plan Check | 8/19/2009 | | 8/19/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/19/2009 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/19/2009 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/19/2009 | | 8/19/2009 | | DONE |
|
|
|
|
Telephone call | | | 8/19/2009 | | DONE |
|
|
|
t/c w jeff anderson at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/19/2009 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/19/2009 | | DONE |
|
|
|
|
Application received | | | 8/14/2009 | | |
|
|
|
|