Miscellaneous action | | | 1/6/2010 | | DONE |
|
|
|
Fire alarm plans taken to records for scanning.
|
INSP-Final Inspection | 12/16/2009 | 12/18/2009 | 12/18/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Alarm Testing | 12/14/2009 | 12/15/2009 | 12/15/2009 | A | FAIL |
Troy Cobbley
|
|
|
fire alarm panel interconnects to NAC panels all tested OK. Interconnections with fire sprinkler devices tested OK. Corrections needed. Refer to on site city approved drawings. Corrections needed include (but are not limited to) overspaced notification devices, missing notificaion, device placement and type not matching plans, smoke detectors for door release mounted incorrectly, smoke above panel is incorrectly placed, however contractor stated will delete rather than move. Ralph to fax signal report for verification.
|
INSP-Alarm Testing | 12/14/2009 | 12/14/2009 | 12/14/2009 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for tomorrow per Ralph Phone #: ###-####
|
FIR-Aging Inspection | 12/14/2009 | 12/14/2009 | 12/14/2009 | | NR |
Troy Cobbley
|
|
|
Per Ralph this will be called in for tomorrow.
|
Issue and Print Permit | | | 9/11/2009 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 8/24/2009 | | 9/10/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
9/10/2009 08:45:23 SLC - activity updated through activity FIRA24 from case FIR09-00507.
|
Alarm Plan Check | 9/10/2009 | | 9/10/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See redlines and review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 9/10/2009 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Inspection Record Card- Fire | 9/10/2009 | | 9/10/2009 | | DONE |
|
|
|
|
Telephone call | | | 9/10/2009 | | DONE |
|
|
|
left message w julie for ralph at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 9/10/2009 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/9/2009 | | |
Stephanie L. Cobbley
|
|
|
Rec'd 2 copies of plans
|
Miscellaneous action | | | 9/1/2009 | | DONE |
Tisha Gallop
|
|
|
picked up failed plans
|
1st review completed | | | 8/31/2009 | | DONE |
|
|
|
|
Alarm Plan Check | 8/31/2009 | | 8/31/2009 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plans denied. Contractor to pick up redlined plans and review comments.
|
Miscellaneous action | | | 8/31/2009 | | DONE |
|
|
|
Review comments faxed to contractor
|
Application received | | | 8/24/2009 | | |
|
|
|
|