Permit Information
Permit NumberFIR09-00516
StatusFinaled
Name ALLIED GENERAL FIRE & SECURITY
Site Address 320 N ALLUMBAUGH
Project NameDetox Center
Customer Number 
ePlanReview 
Description
2/19/10: PLAN MODIFICATION
This plan modification is to provide an AES RF radio panel in place of the previously submitted DACT. In addition the previous mark-ups and comments have been addressed.

This fire alarm permit is to provide a new manual fire alarm system in a new building. System to include sprinkler monitoring, a manual pull station, smoke detection, notification, HVAC and damper shutdown.

Associated building permit: BLD09-00077 (Region Four Substance Abuse and Mental Health Crisis Center) - To construct a 9,189 sq. ft. building for use as and "I-2" occupancy care & treatment facility. This building is fully sprinklered as required for occupancy use group. Work includes perimeter footings, foundation, floor/wall/roof construction, interior walls to create rooms & support areas for short term stay / treatment rooms, staff observation and work stations and accessible restrooms & bathing facilities throughout building; installation of electrical, mechanical, plumbing, sprinkler & alarm systems, interior & exterior finishes & millwork; and all associated site work. drs (CUP08-00139) (DRH08-00404)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  2/26/2010 DONE
fire alarm plans taken to records for scanning
INSP-Final Inspection2/24/20102/24/20102/24/2010APASS
DetailsForrest France
Correction items verified for completion, fire alarm testing passed, permit work approved for final status, contractor to post map at the panel as discussed.
INSP-Final Inspection2/23/20102/23/20102/23/2010AFAIL
DetailsForrest France
Several items noted during field inspection include; incorrect cd ratings at appliances in lobby 214 and hallway 213, sd at hallway 131 too close to an HVAC grill, notification device at hallway 129 overspaced off the end of the corridor, noted 14ga wire at notification circuts where 16ga is shown per plan, missing the smoke detector at lobby 102, strobe location at RR 107 has been moved, missing horn at B-2-13 EOL, plans show a strobe only at vestibule 201, hi/lo pressure switch not used per matrix, damper at ID S15 is not functional, sample tube at the duct detector does not appear to be supported or extend through the ductwork at the other side- see plan note #4, offsite monitoring reports the incorrect building address to dispatch. NOTE: Most issues repaired or adjusted while on site, the balance of system testing passed, remainder of outstanding items to be re-tested tomorrow as discussed. Request a copy of the list of signals sent today including correct address at next site visit. Added relay for the delayed egress hardware tested okay.
INSP-Sprinkler Rough-in/Hydro2/22/20102/23/20102/23/2010PCANC
DetailsForrest France
Dave Dilley is doing the inspection. Inspection requested from web by: Mike Brown Phone #: ###-#### Inspection cancelled from web by: Patricia Smith
INSP-Alarm Testing2/19/20102/22/20102/22/2010PCANC
DetailsTroy Cobbley
Cancel per Mike.
Plan assigned to (Stephanie)2/16/2010 2/19/2010 DONE
DetailsStephanie L. Cobbley
2/19/2010 07:52:31 SLC - activity updated through activity FIRA24 from case FIR09-00516.
Alarm Plan Check2/19/2010 2/19/2010 PASS
DetailsStephanie L. Cobbley
see redlines and review comments
PLANS TAKEN FRONT DESK ALARM  2/19/2010 DONE
approved redlined plans available at front counter
Inspection Record Card- Fire2/19/2010 2/19/2010 DONE
DetailsDarla L Downs
Permit Ready to Issue  2/19/2010 DONE
Telephone call  2/19/2010 DONE
called permit ready
(F) Reprint permit  2/19/2010 DONE
CHANGE STATUS TO (ISS)  2/19/2010 DONE
Telephone call  2/18/2010 DONE
Called Joe at Allied General to let him know the plans he provided for the "Plan Modification" did not have my previous comments and/or redlines incorporated, and that I would need those addressed in order to approve them. He stated he would have them to my by tomorrow morning. I let him know that depending on what time he got them here, I might not have them done until Monday. He stated that he understood.
Plan resubmittals received  2/16/2010 DONE
FIR-Aging Inspection12/3/200912/3/200912/3/2009 NR
DetailsTroy Cobbley
Work is in progress. The building is still under construction.
Plan assigned to (Stephanie)8/27/2009 9/3/2009 DONE
DetailsStephanie L. Cobbley
9/3/2009 10:34:13 SLC - activity updated through activity FIRA24 from case FIR09-00516.
1st review completed  9/3/2009 DONE
Alarm Plan Check9/3/2009 9/3/2009 PASS
DetailsStephanie L. Cobbley
See redlines and review comments
PLANS TAKEN FRONT DESK ALARM  9/3/2009 DONE
Approved redlined plans available at front counter
Inspection Record Card- Fire9/3/2009 9/3/2009 DONE
Details
Telephone call  9/3/2009 DONE
Details
left vm for ken webster at ###-#### - permit ready and fees given
Permit Ready to Issue  9/3/2009 DONE
Details
Issue and Print Permit  9/3/2009 DONE
Application received  8/27/2009