Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR09-00577
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 827 E PARK BLVD STE 100 & 120
Project NamePEAK BROADCASTING
Customer Number 
ePlanReview 
Description
Fire Work Scope:

The Fire Sprinkler Scope of work consists of adding and relocating seven sprinklers to accommodate new ceiling and wall configurations.

Plan Modification Scope:

Add and relocate sprinklers due to field inspection comments. All areas are ballooned. Only the ballooned areas were reviewed.

(PEAK BROADCASTING - Morrison Foundation Building - STE# 100) Permit is to combine the two first floor tenants into a 9,765 square foot whole floor tenant and remove the interior unenclosed stair to isolate the second floor into two tenant spaces (suite 201 / 8,647 square feet and suite 200 / 1,362 square feet). Approval per approved plans on file. Work to include: [construction of interior non-bearing walls to create five offices, one storage room, a receptionist area, and a work room], demo existing unenclosed stairwell and infill with original const., relocating existing lighting, relocate existing ducts and diffusers, new doors and hardware, new accessible sales and service counter, and interior finishes in compliance with chapter 8 of the 2006 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. *TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  1/6/2010 DONE
DetailsTim Frost
Taken to scanning
INSP-Final Inspection10/22/200910/22/200910/22/2009PPASS
DetailsForrest France
Fire sprinkler permit okayed for final, contractor to replace one escutcheon today as discussed.
INSP-Sprinkler Rough-in10/20/200910/20/200910/20/2009PPART
DetailsForrest France
Scope of fire sprinkler work per revised permit documents passed inspection and okayed for cover, final pending ceiling tile and escutcheons.
CHANGE STATUS TO (ISS)  10/19/2009 DONE
(F) Reprint permit  10/19/2009 DONE
Plan assigned to (Tim)10/15/2009 10/16/2009 DONE
DetailsTim Frost
10/16/2009 13:42:54 TRF - activity updated through activity FIRA22 from case FIR09-00577.
Sprinkler Plan Check10/16/2009 10/16/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  10/16/2009 DONE
DetailsTim Frost
1st review completed  10/16/2009 DONE
DetailsTim Frost
Inspection Record Card- Fire10/16/2009 10/16/2009 DONE
Details
Telephone call  10/16/2009 DONE
Details
t/c w jeff anderson at ###-#### - permit (plan mod) ready and fees given
Permit Ready to Issue  10/16/2009 DONE
Details
Plan resubmittals received  10/15/2009 DONE
received 1 application and 3 sets of plans
INSP-Sprinkler Rough-in10/12/200910/13/200910/13/2009AFAIL
DetailsTroy Cobbley
The installation as per the scope of work is passed however additional construction is happening in this tenant space which is effecting the sprinkler coverage. This work needs to be addressed under this permit.
Plan assigned to (Tim)9/21/2009 9/28/2009 DONE
DetailsTim Frost
9/28/2009 14:24:50 TRF - activity updated through activity FIRA22 from case FIR09-00577.
Sprinkler Plan Check9/28/2009 9/28/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  9/28/2009 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  9/28/2009 DONE
DetailsTim Frost
Inspection Record Card- Fire9/28/2009 9/28/2009 DONE
Details
Telephone call  9/28/2009 DONE
Details
t/c w jeff anderson at ###-#### - permit ready and fees given
Permit Ready to Issue  9/28/2009 DONE
Details
Issue and Print Permit  9/28/2009 DONE
Telephone call  9/24/2009 DONE
DetailsTim Frost
Spoke with Jeff Anderson. Discussed the need for additional information in regards to pipe sizing. He said he would get the additional information and get back with me. I am holding the drawings until I hear from him,
Application received  9/21/2009