INSP-Final Inspection | 2/9/2010 | 2/10/2010 | 2/10/2010 | P | PASS |
Forrest France
|
|
|
Verified plan resubmittals, fire sprinkler permit finaled.
|
Sprinkler Plan Check | 2/4/2010 | | 2/4/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
revised plans approved by onsite plan review per T. Cobbley.
|
PLANS TAKEN FRONT DESK ALARM | | | 2/4/2010 | | DONE |
|
|
|
|
1st review completed | | | 2/4/2010 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/4/2010 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 2/1/2010 | 2/3/2010 | 2/3/2010 | P | PART |
Forrest France
|
|
|
Final pending updated plans for field modifications beyond scope of original permit work. Installation appears satisfactory, rough-in passed.
|
FIR-Aging Inspection | 1/1/2010 | 1/1/2010 | 1/6/2010 | | DEFR |
Forrest France
|
|
|
Pending site inspection request.
|
Sprinkler Plan Check | 10/2/2009 | | 10/2/2009 | | PASS |
Troy Cobbley
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 10/2/2009 | | DONE |
Troy Cobbley
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2009 | | DONE |
Tim Frost
|
|
|
|
Issue and Print Permit | | | 10/2/2009 | | DONE |
|
|
|
|
Plan assigned to (Scott) | | | 9/25/2009 | | DONE |
Sam Rogers
|
|
|
This permit was created on the web by Jack Fieselman
|
Plan assigned to (SAM) | | | 9/25/2009 | | DONE |
|
|
|
This permit was created on the web by Jack Fieselman
|