Miscellaneous action | | | 12/3/2009 | | DONE |
|
|
|
FA plans taken to records for scanning
|
INSP-Final Inspection | 11/17/2009 | 11/17/2009 | 11/17/2009 | A | PASS |
Forrest France
|
|
|
Fire alarm permit work finaled.
|
INSP-Final Inspection | 11/12/2009 | 11/13/2009 | 11/13/2009 | A | PART |
Forrest France
|
|
|
Noted correction items repaired, functional testing and signals sent completed satisfactory, need to provide accurate as-builts and NFPA record of completion forms prior to final approval.
|
INSP-Final Inspection | 11/9/2009 | 11/10/2009 | 11/10/2009 | A | NR |
Forrest France
|
|
|
Per contractor sync issues are not yet resolved.
|
INSP-Final Inspection | 11/9/2009 | 11/9/2009 | 11/9/2009 | P | CANC |
Forrest France
|
|
|
Chris Farnsworth Phone #: ###-#### Inspection cancelled from web by: Diane Turner
|
INSP-Final Inspection | 11/3/2009 | 11/3/2009 | 11/3/2009 | P | FAIL |
Forrest France
|
|
|
Noted one overspaced notification device, one obstructed horn/strobe at the engineer room, one existing strobe is mounted too high, per contractor new and existing notification circut appliances are not in synchronization.
|
Inspection Record Card- Fire | 10/8/2009 | | 10/8/2009 | | DONE |
|
|
|
|
Telephone call | | | 10/8/2009 | | DONE |
|
|
|
left vm for bret at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/8/2009 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/8/2009 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 9/29/2009 | | 10/7/2009 | | DONE |
Stephanie L. Cobbley
|
|
|
10/7/2009 15:53:08 SLC - activity updated through activity FIRA24 from case FIR09-00587.
|
Telephone call | | | 10/7/2009 | | DONE |
|
|
|
Spoke with Diane at Mountain Alarm and explained that the re-submitted plans provided battery calculations for the main FACP (which they are not adding to) but not battery calcs for the extender panel (which they are adding to). In addition, I let her know that the one-line was still not consistent with the information I requested previously. I let her know that if she could fax or email me the information by the end of the day that would be acceptable, otherwise I would need to fail the drawings. She stated she would call today and let me know whether or not she'd be able to get the information to me this week, as Bret is out of state at a conference and would be the one to get the information from.
|
Alarm Plan Check | 10/7/2009 | | 10/7/2009 | | PASS |
Stephanie L. Cobbley
|
|
|
See review comments and redlined plans
|
PLANS TAKEN FRONT DESK ALARM | | | 10/7/2009 | | DONE |
|
|
|
Approved redlined plans available at front counter
|
Plan resubmittals received | | | 10/6/2009 | | |
Tisha Gallop
|
|
|
received application and two copies of submittal documents and plan sheets FA-1, FA-2; taken to fire review
|
1st review completed | | | 9/30/2009 | | DONE |
|
|
|
|
Alarm Plan Check | 9/30/2009 | | 9/30/2009 | | FAIL |
Stephanie L. Cobbley
|
|
|
See review comments and redlined drawings
|
Miscellaneous action | | | 9/30/2009 | | DONE |
|
|
|
Plans denied...review comments faxed to contractor.
|
Telephone call | | | 9/30/2009 | | DONE |
|
|
|
Spoke with Bret at Mountain Alarm to let him know I would need to deny the plans. I summarized the items needed for resubmittal and let him know I would fax him the review comments for more detailed information and that the denied redlined plans would be available for pick up at his convenience.
|
Miscellaneous action | | | 9/30/2009 | | DONE |
|
|
|
contractor picked up denied plans
|
Application received | | | 9/29/2009 | | |
|
|
|
|