Miscellaneous action | | | 1/14/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 4/23/2010 | 4/23/2010 | 4/26/2010 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit final approved.
|
INSP-Sprinkler Rough-in | 4/21/2010 | 4/21/2010 | 4/21/2010 | A | PART |
Forrest France
|
|
|
Forward flow testing completed satisfactory, recieved record drawings for field modifications.
|
INSP-Sprinkler Rough-in | 4/9/2010 | 4/9/2010 | 4/9/2010 | A | PART |
Forrest France
|
|
|
Noted correction items listed 4/1 verified for completion, rough-in passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/5/2010 | 4/6/2010 | 4/6/2010 | A | PART |
Forrest France
|
|
|
Completed satisfactory hydrostatic test of the overhead wet systems including new and existing piping.
|
INSP-Sprinkler Rough-in/Hydro | 4/5/2010 | 4/5/2010 | 4/5/2010 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 4/1/2010 | 4/1/2010 | 4/1/2010 | A | PART |
Forrest France
|
|
|
Completed overhead inspections at all new areas including the dry storage, east and west recieving, cooler #3, vat room, cultured packaging and production and dock. CIP room is not finished at this time, discussed hydrostatic testing schedule, noted a fire alarm permit to include new riser and antifreeze loop monitor points will be necessary. Red lined correction items on stamped plan set (seismic bracing, pend. outlet on dry system, etc.) including field modifications to be indicated on record drawings for relocated main, FDC, new SW heads. Riser needs tagged and head boxes mounted, RP and DCVA tested while on site.
|
INSP-Sprinkler Rough-in | 3/2/2010 | 3/3/2010 | 3/3/2010 | A | PART |
Forrest France
|
|
|
Inspection for fire resistive coatings at exposed wood surfaces above the drop ceilings at the new restroom entry vestibules.
|
INSP-Sprinkler Rough-in/Hydro | 2/26/2010 | 2/26/2010 | 2/26/2010 | P | PART |
Forrest France
|
|
|
Concluded satisfactory 24 hr. air test @ 2:00PM 2/26 for overhead dry system install. Also okayed ceiling cover at the mens and womens restrooms and two new offices, new RR vestibules are not approved for cover due to pending fire resistive coatings at exposed wood.
|
INSP-Sprinkler Rough-in/Hydro | 2/25/2010 | 2/25/2010 | 2/26/2010 | P | PART |
Forrest France
|
|
|
Begin 24 hr air testing of the new dry system piping at the SE cooler area at 50 psig. @ 2:00PM 2/25. Also completed hydrostatic testing of the new antifreeze loop at the north dock.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2010 | 2/24/2010 | 2/24/2010 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic testing for the new cooler area at the SE corner of the building completed satisfactory after repairs made while on site, noted insufficient seismic clearance at the main through the west wall- contractor to provide flex couplings spaced per NFPA 13 as discussed at this location.
|
INSP-Sprinkler Rough-in | 2/12/2010 | 2/12/2010 | 2/19/2010 | P | PART |
Forrest France
|
|
|
On site visit regarding fire sprinkler coverage at the new restroom entry vestibules and concealed spaces. Included site walkthrough of building additions, dock areas, new wet riser and FDC at the east side. Discussed existing system and hydrostatic testing schedule.
|
INSP-Sprinkler Rough-in | 1/29/2010 | 1/29/2010 | 2/1/2010 | P | PART |
Forrest France
|
|
|
Inspection for the new wet riser, DCVA, and UG riser okayed with the exception of insufficient clearance provision where the riser stub will meet the new floor slab- to be done prior to pour as discussed.
|
INSP-Conference | 2/1/2010 | 2/1/2010 | 2/1/2010 | A | DONE |
Forrest France
|
|
|
Regarding UG supply pipe specs per NFPA ch. 8 and 10.
|
Plan assigned to (Tim) | 11/10/2009 | | 11/12/2009 | | DONE |
Tim Frost
|
|
|
11/12/2009 13:18:47 TRF - activity updated through activity FIRA22 from case FIR09-00642.
|
Sprinkler Plan Check | 11/12/2009 | | 11/12/2009 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 11/12/2009 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2009 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 11/12/2009 | | 11/12/2009 | | DONE |
|
|
|
|
Telephone call | | | 11/12/2009 | | DONE |
|
|
|
t/c w jeff anderson at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 11/12/2009 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/12/2009 | | DONE |
|
|
|
|
Application received | | | 11/10/2009 | | |
|
|
|
|
Pending Assignment by SAM | 11/10/2009 | | 11/10/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
11/10/2009 10:18:27 ALR - activity updated through activity FIRA158 from case FIR09-00642.
|