Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR09-00656
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 1335 S MAPLE GROVE RD
Project NameBLACK EAGLE #1
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of adding and relocating sprinklers to accommodate new wall and ceiling configuration. The existing system has a 4"x1 ½"x1 ¼" grid. However, the plans do not show the entire system. It appears an additional main may exist. The existing system was reported designed for 120sf with .20/1500. The new TI is 225sf with .15/1500. The existing water supply is reported as S=65, R=20, Q=2500

(BROWN MACKIE COLLEGE - SOUTHEAST CORNER OF BUILDING) This building is fully fire sprinklered for area increase. To create a 7,144 square foot tenant space within an existing 44,703 square foot, one story building. This tenant space will be an educational occupancy for students above the 12th grade. It will be a teaching facility for educational programs including veterinary technician and criminal justice. It will include classrooms, criminal justice labs, pet treatment, pet surgical lab, and pet boarding. There will be an X-ray machine and an oxygen storage room. Work is to include interior nonbearing walls, a nonrated corridor, 2 restrooms accessible to the disabled, 1 unisex restroom accessible to the disabled, movable pet kennels, a folding partition, interior doors, interior windows, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  1/6/2010 DONE
DetailsTim Frost
Taken to scanning.
INSP-Final Inspection12/28/200912/29/200912/29/2009APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro12/8/200912/9/200912/9/2009PPART
DetailsTroy Cobbley
The sprinkler piping in the new tenant space can be covered. The new upright sprinkler heads in the adjoining spaces is not yet complete.
INSP-Sprinkler Rough-in11/20/200911/20/200911/20/2009PPASS
DetailsTroy Cobbley
See the city approved plans for sprinkler piping above the hard lids that is ok to cover.
Issue and Print Permit  11/20/2009 DONE
Plan assigned to (Tim)11/16/2009 11/17/2009 DONE
DetailsTim Frost
11/17/2009 12:56:44 TRF - activity updated through activity FIRA22 from case FIR09-00656.
Sprinkler Plan Check11/17/2009 11/17/2009 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  11/17/2009 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  11/17/2009 DONE
DetailsTim Frost
Permit Ready to Issue  11/17/2009 DONE
Inspection Record Card- Fire11/17/2009 11/17/2009 DONE
DetailsBarbara Stitt
Telephone call  11/17/2009 DONE
DetailsBarbara Stitt
Called Jeff With DeBest Fire and told him that permit is ready & fees due///11-17-09 @ 4:00pm BAS
Application received  11/16/2009